Primary construction activities for the week of 12/09 thru 12/13 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Continue framing soffit
- CANOPIESWest Canopy V102:Finish installing electrical and gyping lids *Installing WRB
- Commons Wing Soffit:Continue installing trim and metal soffit panels
- Lab Wing Soffit:Continue installing trim and wood soffit
- WINDOWS & SIDING
- Auditorium – South Elevation:
- Continue finishing siding *
- INTERIOR BUILDOUT
- Commons Wing – Auditorium:
- Start installing electrical
- Commons Wing – Innovation Lab:
- Painting
- Installing ACT grid
- Commons Wing – Level 1 – Bathrooms &
A/V Hard Lid Rooms:
- Finish installing MEP in hard lids
- MEP inspection
- Start gyping walls and lids
- Commons Wing – Level 2 – Design 3D &
Art Studio:
- Installing ceiling grid and MEP in ceilings
- Inspection for MEP in ceilings
- Commons Wing – Level 2 – Sound Control
and Vestibules:
- Finishing lids and walls
- Painting and installing ceiling grid in Sound Control
- Lab Wing – Level 1 – Mechanical & Back of House:
- Continue installing panels and feeders in electric rooms
- Lab Wing – Level 1 – Commons Spaces
(Café & Fireplace):
- Installing transformer and panels
- Start grinding floors and install electrical in walls
- Lab
Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Finish installing MEP at hard lids *
- MEP inspection for hard lids *
- Start gyping walls and lids
- Lab Wing – Level 2 – Rough-in:
- Continue installing cable tray at OTS and Commons
- Lab
Wing – Level 2 – Commons Spaces:
- Installing casework and windowsills
- Lab
Wing – Level 2 – Labs:
- Finish overhead electrical in lab area
- Completing floor moisture mitigation
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Finishing MEP in grid
- Lab Wing – Level 3 Rough-in:
- Gyping South and East walls
- Finishing walls, OTS insulation, and top-of-wall at SE area
- Start gyping North walls
- Installing electrical on North and West
- Start installing MEP in OTS, offices, and SE area
- Roof – West Penthouse ELEV Equip Room:
- Finish installing shaft frame, gyp, and finish *
- Start installing disconnects