Primary construction activities for the week of 12/09 thru 12/13 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue framing soffit
  • CANOPIESWest Canopy V102:Finish installing electrical and gyping lids *Installing WRB
  • Commons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Continue installing trim and wood soffit
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Continue finishing siding *
  • INTERIOR BUILDOUT
  • Commons Wing – Auditorium:
    • Start installing electrical
  • Commons Wing – Innovation Lab:
    • Painting
    • Installing ACT grid
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish installing MEP in hard lids
    • MEP inspection
    • Start gyping walls and lids
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Installing ceiling grid and MEP in ceilings
    • Inspection for MEP in ceilings
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finishing lids and walls
    • Painting and installing ceiling grid in Sound Control
  • Lab Wing – Level 1 – Mechanical & Back of House:
  • Continue installing panels and feeders in electric rooms
  • Lab Wing – Level 1 – Commons Spaces (Café & Fireplace):
    • Installing transformer and panels
    • Start grinding floors and install electrical in walls
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish installing MEP at hard lids *
    • MEP inspection for hard lids *
    • Start gyping walls and lids
  • Lab Wing – Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Commons Spaces:
    • Installing casework and windowsills
  • Lab Wing – Level 2 – Labs:
    • Finish overhead electrical in lab area
    • Completing floor moisture mitigation
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid
  • Lab Wing –  Level 3 Rough-in:
    • Gyping South and East walls
    • Finishing walls, OTS insulation, and top-of-wall at SE area
    • Start gyping North walls
    • Installing electrical on North and West
    • Start installing MEP in OTS, offices, and SE area
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish *
  • Start installing disconnects