Primary construction activities for the week of 09/16 thru 09/20 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Finish installing siding
    • Begin Installing Zinc Roofing
  • Lab Wing Main Roof:
    • Continue to install the exterior concrete topping slabs
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • – South Elevation:
  • Commons Wing – North Elevation:
  • Commons Wing – East Elevation:
  • Commons Wing – West Elevation:
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
  • Lab Wing – North Elevation:
  • Install Curtain Wall Center
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
  • Auditorium – East Elevation:
    • Finish installing windows
    • Begin Backer rod and caulk
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
  • Continue installing vertical siding MWC
  • Auditorium – North Elevation:
    • Finish installing windows
    • Backer rod and caulk
    • Begin installing glass and pressure bar
    • Install flashing and trim
  • INTERIOR BUILD-OUT
  • Rough in Framing Commons Wing
  • Begin build soffit and wall above and below
  • Begin to install top out for MEP to start 2nd floor
  • Begin installing MEP and fire Protection in auditorium high ceiling
  • Begin MEP in Walls on 2nd floor
  • MEP soffit and wall above
  • Install Bathroom carriers
  • Begin to install bathroom carriers
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the first floor
  • Rough in Remaining First Floor:
  • Install Top Out
  • Begin top out finish
  • Lab Wing Level 2 – Rough-in:
    • to install hydronic piping in OTS Commons
    • fire protection in OTS commons
    • Continue to install electrical in OTS Commons
    • Continue to install Plumbing in OTS Commons
    • Continue to install Duct Work in OTS Commons
    • Finish all paint on 2nd floor
  • Level 3:
  • Roof Level:
  • Finish MEP in walls
  • Finish installing Elevator equipment
  • Begin Installing fire protection
  • Install Gyp
  • Finish Gyp
  • Elevators:
  • Stairs:
  • SITE IMPROVEMENTS
  • ODFW Parking and Sidewalks:
  • Ramp:
    • Install edge form and rebar
    • Begin Pouring ramp slab
    • Install storm channel and electrical
    • Begin cutting to grade
Print Friendly, PDF & Email

Leave a reply

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong> 

required