Primary construction activities for the week of 08/05 thru 08/09 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • Lab Wing – South Elevation:
    • Finish installing flashings and window steel
  • Auditorium – North Elevation:
    • Finish installing temp window protection (if needed) *
  • Auditorium – East Elevation:Auditorium – South Elevation:
    • Finish installing Window Steel
  • Auditorium – West Elevation:
    • Finish installing temp window protection if needed
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding MWC
  • Lab Wing – North Elevation:
    • Finish installing vertical siding MWC
    • Begin installing beauty cap and flashing
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
    • Begin installing horizontal cleat
  • Auditorium – East Elevation:
    • Install flashings and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows
    • Begin installing flashings and trim
    • Begin back rod and caulk
  • Auditorium – North Elevation:
    • Finish installing vertical Z girt
    • Finish Installing windows
    • Begin to install flashings and trim
  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
  • Lab Wing Level 2 – Rough-in:
    • Finish Stuff and spray for STC’s
  • Roof Level:
  • Finish MEP in Walls
  • Install Gyp
  • Elevators:
  • Procure Elevator
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODFW Parking and Sidewalks:
    • Pave Parking first lift
    • Pave parking 2nd lift
    • Excavate Public Rain Garden after Paving
  • Ramp:
    • Finish backfilling up to the fluid applied weather protection
    • Install the complete bentonite and fluid applied weather protection