Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- Low Roof Auditorium:
- Start installing roof
- Lab Wing Main Roof:
- Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
- Penthouses:
- Installing water barrier
- Lab High Roof West:
- Continue installing roof
- FRAMING SHEATING (2nd & 3rd Floor)
- Lab Wing – South Elevation:
- Finish installing temp window protection (if needed) *
- FRAMING SHEATING (1st Floor)
- Lab Wing – South Elevation:
- Installing window steel at head & sill, flashings, and air & water barrier
- Auditorium – North Elevation:
- Finish installing steel studs
- Start installing exterior gyp
- Auditorium – East Elevation:
- Start installing flashings, window steel, and temp window protection (if needed)
- Auditorium – South Elevation:
- Continue installing air & water barrier, window steel, and flashings **
- Start installing flashings, window steel, and temp window protection (if needed)
- Auditorium – West Elevation:
- Finish installing steel studs **
- Start installing exterior gyp *
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- Continue installing vertical wood cladding
- Lab Wing – North Elevation:
- Continue installing vertical wood cladding and windows
- Lab Wing – East Elevation:
- Finish installing horizontal cleat (pulled off to go to South side) *
- Installing flashings and trim
- Start installing backer rod and caulk and vertical wood cladding *
- Lab Wing – South Elevation:
- Continue installing windows, flashings & trim, and horizontal cleat
- Auditorium – East Elevation:
- Start installing windows and vertical Z girt
- Auditorium – South Elevation:
- Continue installing vertical Z girt
- INTERIOR BUILDOUT
- Mechanical & Back of House:
- Finish installing gyp top out & electrical rooms, tape & finish one side top out, stuffing and spraying for STC’s, sound board at OTS ceilings, and extending down rods
- Lab Wing Level 2 – Rough-in:
- Finish installing gyp top out one side of walls at duct locations
- Continue installing MEP in Labs
- Start tape and finish one side top out
- SITE IMPROVEMENTS
- Mechanical Enclosure M0101:
- Setting Generator and ACCH-101
- ODF&W Parking and Sidewalks:
- Start installing rebar for sidewalks and mono curbs *
- Excavating for Rain Garden #2 *