Primary construction activities for the week of 06/24 thru 06/28 will consist of the following:

|   * = Start or Finish was delayed    |   ** Start or Finish postponed   |

  • ROOFING
  • Evacuation Ramp:
    • Install expansion joint and trench drain
    • Install hot rubber roofing (moved to Lab to strip in)
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Finish installing framing *
    • Start installing sheathing *
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed)

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
  • Finish installing window steel at head & sill, flashings, air & water barrier, and temp window protection (if needed)*
    • Lab Wing – East Elevation:
  • Finish installing temp window protection (if needed) *
    • Lab Wing – South Elevation:
  • Start installing exterior gyp
  • Start installing air & water barrier, flashings, and window steel at head & sill
  • Auditorium – North Elevation:
    • Continue installing steel studs
      • Auditorium – South Elevation:
    • Installing air & water barrier, window steel, and flashings
  • Auditorium – West Elevation:
    • Installing steel studs
    • Start installing exterior gyp

 

 

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing vertical wood cladding and windows
  • Lab Wing – East Elevation:
    • Finish installing horizontal cleat
    • Installing flashings and trim
    • Start installing backer rod and caulk * and vertical wood cladding
  • Lab Wing – South Elevation:
    • Finish installing vertical Z girt
    • Continue installing windows
    • Start installing flashings and trim
  • Auditorium – South Elevation:
    • Start installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Start stuffing and spraying for STC’s **
    • Start tape and finish one side top out
  • Lab Wing Level 2 – Rough-in:
    • Finish framing walls (starting at E/3 clockwise)
    • Continue installing MEP in Labs
    • Start installing gyp top out one side of walls at duct locations

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Finish forming sidewalks & steps and placing sidewalk and steps
  • ODF&W Parking and Sidewalks:
    • Start forming sidewalks and mono curbs *
    • Importing rock & rough grade and excavating for Rain Garden #2

 