Primary construction activities for the week of 04/15 thru 04/19 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • East Storage Room & Northeast Wall (Pour 4):
      • Closing formwork, pouring, and stripping wall
    • South Wall East Portion (Pour 5):
      • Setting wall formwork
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips early next week
  • Slab on Metal Deck
    • Zone 5 Level 3:
      • Curing deck for reshore removal
    • Zone 4 Level 2:
      • Finish installing rebar; installing top embeds and pouring deck
    • Zone 5 Level 2
      • Installing rebar, top embeds, and pouring deck
  • Slab on Grade
    • Zone 1:
      • Installing top embeds and pouring slab
    • Zone 2:
      • Installing rebar, top embeds, and pouring slab
  • Roofing
    • Lab Wing Main Roof:
      • Forming and installing rebar at West curbs
      • West Penthouse:
        • Welding, bolting, and decking
      • East Penthouse:
        • Welding, bolting, and decking
      • Lab High Roof East:
        • Continue installing roof
      • Lab High Roof West:
        • Continue installing roof
  • Framing Sheeting
    • Lab Wing West & SW Elevation:
      • Installing steel studs
    • Lab Wing North Elevation:
      • Installing steel stud floor clips
    • Lab Wing East Elevation:
      • Installing steel stud floor clips