Primary construction activities for the week of 03/11/2019 thru 03/15/2019:

  • Ramp:
    • Pour 2 (North Radius Wall):
      • Finish stripping wall.
    • Pour 3 (South Wall West):
      • Setting wall and installing rebar.
  • Structural Steel:
    • Stair 2:
      • Finish install of handrails.
    • East Commons (Z1):
      • Finish install of metal decking and closure strips.
    • West Lab Wing (Z3):
      • Installing headed studs.
    • Center Lab Wing (Z4):
      • Finish bolting, plumbing, and welding.
      • Install metal decking and closure strips.
    • East Lab Wing (Z5):
      • Bolting, plumbing, and welding
  • Slab on Metal Deck
    • Z2 Roof:
      • Installing blockouts and down embeds
      • Installing rebar
      • Installing top embeds
    • Z2 L2:
      • Installing blockouts and down embeds
      • Installing rebar
  • Sitework & Utilities
    • Install potable and fire water laterals
  • Mockup:
    • Finish installing siding.