Primary construction activities for the week of 2/11/2019 – 2/12/2019 will consist of:

Core 1: Forming, pouring, and stripping the architectural fur wall.

Ramp: Fabricating walls and setting walls.

Structural Steel:

Stair 1: installing clips and hangers.

Stair 2: Delivery by EOW.

East Commons (Z1): Erecting steel, bolting, plumbing and welding.

West Commons (Z2): Erecting, bolting, plumbing, and welding.

West Lab Wing (Z3): Installing, shear tab clips, and erecting.

Center Lab Wing (Z4): Installing shear tab clips and misc metals.

East Lab Wing (Z5): Installing shear tab and misc metals.

Mockup: Framing, installing steel window surround, backing, weather barrier, and windows.