Primary construction activities for the week of 01/21/2019- 01/25/2019 will consist of:

Core 2- Level 3 will be poured and inside core stripped, then start setting formwork and rebar for Level 4.

Core 3- Level 3 will be poured and stripped, then start setting formwork and rebar for Level 4.

Ramp- Forming and placing rebar at South Wall.

Slab for Level 1 Air Handler Unit- Install vapor barrier, forming, pour pads, and stripping pads.

Mockups- Install steel window surrounds, backing, and weather barrier.

Structural Steel- Installing clips and hangers for stair 1, and installing shear tab clips for east commons (Z1).