Primary construction activities for the week of 10/22 thru 10/26 will consist of the following:

  • Installing asphalt walk at ODFW / West Wing
  • Installing Rebar, pouring, and stripping Continuous Footings
  • Pouring concrete and stripping at East Mat Footing (attached Images)
  • One-side formwork for Shear Walls 1, 2, and 3
  • Installing rebar at Shear Walls 4 and 5
  • Forming and installing rebar for Level 1 of Core 1
  • Forming and installing rebar for Starter Wall at Core 2 & 3

Attached Schedule

2018.10.14.OAC