Primary construction activities for the week of 10/15 thru 10/19 will consist of the following:

  • Installing asphalt walk at ODFW / West Wing
  • Stripping formwork for Shear Wall Footings
  • Forming, placing rebar, and pouring concrete at East Mat Footing
  • Forming, placing rebar, pouring, and stripping Starter Walls at Commons Wing & West Lab Wing