Today, Monday January 14th, 2019 marks some important milestones in the construction of the Magruder Expansion. Starting today, the concrete pour will begin for the clinic’s slab on metal deck roof, which is expected to continue into Wednesday. Also, the start of the structural steel for the lecture hall. Installation will begin on Wednesday and continue through the end of January.
In other events for the Magruder Expansion- the beginning of the week at the clinic exterior framing for the north side of the building will be completed and moving into exterior framing of the east side of the building which will run through the beginning of next week. It’s currently expected that the exterior sheeting installation that begins today will carry into at least the beginning of February. Lastly at the clinic, work for the rain drains will be completed midweek.
At the lecture hall, the majority of the focus is centered around beginning the installation of the structural steel. At the end of the week, work will start on installing a new 12″ storm line for the lecture hall.
The site of the LINAC addition will be busy this week, continuing from last week; the LINAC walls will finish out being stripped, by the end of the week the plumbing and electrical concrete rough-ins should be complete, and continuation of working on the slab edge forms.
Working with the existing Magruder Hall, this week they will be tying into the existing water and running new electrical conduit down the hallway by the lecture hall.
Make sure to stay up to date with the current schedule and work site photos!