Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Continue to form and pour evacuation ramp and eyebrows
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
  • Lab High Roof West:
    • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
    • Install flashings and window steel
  • Auditorium – North Elevation:
    • Finish installing steel studs
    • Start installing exterior gyp
  • Auditorium – East Elevation:
    • Start installing flashings, window steel, and temp window protection (if needed)
      • Auditorium – South Elevation:
    • to install window steel and flashings**
  • Auditorium – West Elevation:
    • Finish Installing weather barrier, window steel, and flashings
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding
  • Lab Wing – North Elevation:
    • Continue installing vertical siding and windows
  • Lab Wing – East Elevation:
    • Continue installing vertical siding
    • Installing windows
    • Start installing backer rod and caulk and vertical wood cladding *
  • Lab Wing – South Elevation:
    • Continue installing windows, flashings & trim, and horizontal cleat
  • Auditorium – East Elevation:
    • Finish installing windows and vertical Z girt
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows flashings and trim
  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms and place all house keeping pads.
  • Lab Wing Level 2 – Rough-in:
    • Install MEP in walls
    • Finish Stuff and spray for STC’s
  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • Fine grade the parking lot to be ready for asphalt
    • Excavating for Rain Garden #2 *
Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Continue to form and pour evacuation ramp and eyebrows
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Installing water barrier
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
  • Continue to install temp window protection where needed
  • Auditorium – North Elevation:
    • Finish installing steel studs
    • Start installing exterior gyp
  • Auditorium – East Elevation:
    • Start installing flashings, window steel, and temp window protection (if needed)
      • Auditorium – South Elevation:
    • Continue to install window steel and flashings**
  • Auditorium – West Elevation:
    • Installing weather barrier, window steel, and flashings

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding
  • Lab Wing – North Elevation:
    • Continue installing vertical siding and windows

 

 

 

 

  • Lab Wing – East Elevation:
    • Continue installing vertical siding
    • Installing windows
    • Start installing backer rod and caulk and vertical wood cladding *
  • Lab Wing – South Elevation:
    • Continue installing windows, flashings & trim, and horizontal cleat
  • Auditorium – East Elevation:
    • Start installing windows and vertical Z girt
  • Auditorium – South Elevation:
    • Continue installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish painting top out for MEP to start, start installing panels/feeders in electric rooms and place all house keeping pads.
  • Lab Wing Level 2 – Rough-in:
    • Install MEP in walls
    • Finish installing gyp top out one side of walls at duct locations
    • Continue tape and finish one side top out

 

  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • FRPS west and south curbs
    • Excavating for Rain Garden #2 *

 

Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • Low Roof Auditorium:
    • Start installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Installing water barrier
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
  • Installing window steel at head & sill, flashings, and air & water barrier
  • Auditorium – North Elevation:
    • Finish installing steel studs
    • Start installing exterior gyp
  • Auditorium – East Elevation:
    • Start installing flashings, window steel, and temp window protection (if needed)
      • Auditorium – South Elevation:
    • Continue installing air & water barrier, window steel, and flashings **
  • Auditorium – West Elevation:
    • Finish installing steel studs **
    • Start installing exterior gyp *

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing vertical wood cladding and windows

 

 

 

 

  • Lab Wing – East Elevation:
    • Finish installing horizontal cleat (pulled off to go to South side) *
    • Installing flashings and trim
    • Start installing backer rod and caulk and vertical wood cladding *
  • Lab Wing – South Elevation:
    • Continue installing windows, flashings & trim, and horizontal cleat
  • Auditorium – East Elevation:
    • Start installing windows and vertical Z girt
  • Auditorium – South Elevation:
    • Continue installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish installing gyp top out & electrical rooms, tape & finish one side top out, stuffing and spraying for STC’s, sound board at OTS ceilings, and extending down rods
  • Lab Wing Level 2 – Rough-in:
    • Finish installing gyp top out one side of walls at duct locations
    • Continue installing MEP in Labs
    • Start tape and finish one side top out

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Setting Generator and ACCH-101

 

  • ODF&W Parking and Sidewalks:
    • Start installing rebar for sidewalks and mono curbs *
    • Excavating for Rain Garden #2 *
Primary construction activities for the week of 06/24 thru 06/28 will consist of the following:

|   * = Start or Finish was delayed    |   ** Start or Finish postponed   |

  • ROOFING
  • Evacuation Ramp:
    • Install expansion joint and trench drain
    • Install hot rubber roofing (moved to Lab to strip in)
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Finish installing framing *
    • Start installing sheathing *
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed)

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
  • Finish installing window steel at head & sill, flashings, air & water barrier, and temp window protection (if needed)*
    • Lab Wing – East Elevation:
  • Finish installing temp window protection (if needed) *
    • Lab Wing – South Elevation:
  • Start installing exterior gyp
  • Start installing air & water barrier, flashings, and window steel at head & sill
  • Auditorium – North Elevation:
    • Continue installing steel studs
      • Auditorium – South Elevation:
    • Installing air & water barrier, window steel, and flashings
  • Auditorium – West Elevation:
    • Installing steel studs
    • Start installing exterior gyp

 

 

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing vertical wood cladding and windows
  • Lab Wing – East Elevation:
    • Finish installing horizontal cleat
    • Installing flashings and trim
    • Start installing backer rod and caulk * and vertical wood cladding
  • Lab Wing – South Elevation:
    • Finish installing vertical Z girt
    • Continue installing windows
    • Start installing flashings and trim
  • Auditorium – South Elevation:
    • Start installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Start stuffing and spraying for STC’s **
    • Start tape and finish one side top out
  • Lab Wing Level 2 – Rough-in:
    • Finish framing walls (starting at E/3 clockwise)
    • Continue installing MEP in Labs
    • Start installing gyp top out one side of walls at duct locations

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Finish forming sidewalks & steps and placing sidewalk and steps
  • ODF&W Parking and Sidewalks:
    • Start forming sidewalks and mono curbs *
    • Importing rock & rough grade and excavating for Rain Garden #2

 

Primary construction activities for the week of 06/17 thru 06/21 will consist of the following:

 * = Start or Finish was delayed

  • ROOFING
  • Evacuation Ramp:
    • Finish Hot rubber roofing *
    • Form and install foam at 1st 3rd of the Ramp
  • High Roof Auditorium:
    • Start installing zinc roofing
  • Low Roof Auditorium:
    • Continue installing foam into Epic deck, insulation, and cover board
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Finish installing framing *
    • Start installing sheathing *
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing air & water barrier
    • Continue installing flashing at pop outs, window steel at pop outs
    • Start installing temp window protection (if needed)

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
  • Finish installing window steel at head & sill, flashings, air & water barrier, and temp window protection (of needed)*
    • Lab Wing – North Elevation:
  • Finish installing window steel at window head & sill, flashings, and air & water barrier, and temp window protection (if needed) *
    • Lab Wing – East Elevation:
  • Finish installing window steel at window head & sill, flashings, and air & water barrier
  • Start installing temp window protection (if needed) *
    • Lab Wing – South Elevation:
  • Continue installing steel studs

 

 

  • Auditorium – North Elevation:
    • Continue installing steel studs
      • Auditorium – South Elevation:
    • Finish installing steel stud floor clips *
    • Continue installing steel studs *
  • Auditorium – West Elevation:
    • Finish installing steel stud floor clips *
  • Innovation Lab:
    • Installing window steel

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing insulation & horizontal cleat, flashings & trim, vertical wood cladding, and windows
  • Lab Wing – East Elevation:
    • Installing flashings and trim
    • Start installing backer rod and caulk
  • Lab Wing – South Elevation:
    • Start installing vertical Z girt and windows

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish installing in-wall MEP at Electrical Rooms *
    • Finish installing gyp top out *
    • Start stuffing and spraying for STC’s
  • Lab Wing Level 2 – Rough-in:
    • Continue installing MEP in Labs
    • Continue framing walls (starting at E/3 clockwise)

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Stripping retaining walls, damp proofing walls, back filling walls, and forming sidewalks & steps
    • Start placing sidewalk and steps at EOW
  • ODF&W Parking and Sidewalks:
    • Finish excavating for Public Rain Garden*
    • Finish balance of storm work *
    • Installing pole base and electrical for exterior light poles
    • Start forming sidewalks and mono curbs
Primary construction activities for the week of 06/10 thru 06/14 will consist of:

  • ROOFING
    • High Roof Auditorium:
      • Finish installing roof
    • Evacuation Ramp:
      • Start Hot rubber roofing *
    • Low Roof Auditorium:
      • Start installing foam into Epic deck
    • Lab Wing Main Roof:
      • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
    • Penthouses:
      • Finish installing framing *
      • Start installing sheathing *
    • Lab High Roof West:
      • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
    • Lab Wing – North Elevation:
      • Finish installing temp window protection (if needed)
    • Lab Wing – East Elevation:
      • Finish installing temp window protection (if needed)
    • Lab Wing – South Elevation:
      • Start installing air & water barrier, window steel at pop outs, and flashing at pop outs

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
      • Finish installing exterior gyp board, window steel at head & sill, flashings, and air & water barrier *
    • Lab Wing – North Elevation:
      • Finish installing window steel at window head & sill, flashings, and air & water barrier, and temp window protection *
    • Lab Wing – East Elevation:
      • Finish installing exterior gyp, air & water barrier, flashings, and window steel at head & sill *
    • Lab Wing – South Elevation:
      • Start installing steel studs *
    • Auditorium – North Elevation:
      • Continue installing steel studs
    • Auditorium – South Elevation:
      • Finish installing steel stud floor clips *
      • Continue installing steel studs *
    • Auditorium – West Elevation:
      • Finish installing steel stud floor clips *

 

  • WINDOWS & SIDING
    • Lab Wing – West Elevation:
      • Continue installing siding horizontal cleat
      • Start installing vertical siding wood cladding *
    • Lab Wing – North Elevation:
      • Continue installing windows
      • Start installing flashings and trim
    • Lab Wing – East Elevation:
      • Installing windows
      • Start installing vertical z girt

 

  • INTERIOR BUILDOUT
    • Mechanical & Back of House:
      • Finish installing in-wall MEP at Electrical Rooms
      • Finish installing gyp top out
    • Lab Wing Level 2 – Rough-in:
      • Continue installing MEP in Labs
      • Continue framing walls (starting at E/3 clockwise)

 

  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101:
      • Installing rebar, pouring, and stripping Generator Pad and footings *
    • ODF&W Parking and Sidewalks:
      • Finish balance of storm work *
      • Installing Storm FC Manhole No.1 and storm chambers
      • Excavating for Public Rain Garden

 

  • SITEWORK & UTILITIES
    • Finish installing potable water and fire water laterals

 

 * = Start or Finish was delayed

Primary construction activities for the week of 06/03 thru 06/07 will consist of the following:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • ROOFING
    • High Roof Auditorium:
      • Continue installing roof
    • Evacuation Ramp:
      • Finish installing handrails
      • Start Hot rubber roofing
    • Penthouses:
      • Finish installing framing
      • Installing sheathing
    • Lab High Roof West:
      • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
    • Lab Wing – North Elevation:
      • Finish installing flashings at pop outs
      • Continue installing temp window protection (if needed)
    • Lab Wing – East Elevation:
      • Finish installing flashings at pop outs and air & water barrier
    • Lab Wing – South Elevation:
      • Finish installing steel studs
      • Installing exterior gyp
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
      • Finish installing window steel at window head & sill, flashings, and air & water barrier
      • Start installing temp windows (if needed)
    • Lab Wing – North Elevation:
      • Finish installing exterior gyp
      • Start installing window steel at window head & sill, flashings, and air & water barrier
      • Installing temp window protection (if needed)
    • Lab Wing -East Elevation:
      • Finish installing steel studs (was postponed)
      • Installing exterior gyp
      • Start installing window steel at window head & sill, flashings, and air & water barrier at EOW
      • Installing temp window protection (if needed)
    • Lab Wing – South Elevation:
      • Start installing steel studs
    • Auditorium – South Elevation:
      • Continue installing steel studs
      • Start installing exterior gyp
    • Auditorium – West Elevation:
      • Start installing steel studs
    • Auditorium – North Elevation:
      • Start installing steel studs
  • WINDOWS & SIDING
    • Lab Wing – West Elevation:
      • Continue installing siding horizontal cleat
      • Start installing vertical siding wood cladding
    • Lab Wing – North Elevation:
      • Continue installing vertical Z girts and windows
    • Lab Wing – East Elevation:
      • Start installing vertical Z girts and windows
  • INTERIOR BUILDOUT
    • Mechanical & Back of House:
      • Finish framing walls
      • Installing in-wall MEP at Electrical Rooms
      • Start installing gyp top out
    • Lab Wing Level 2 – Rough-in:
      • Continue installing MEP in Labs
      • Start framing walls (starting at E/3 clockwise)
    • Stair 1:
      • Pouring stairs
  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101:
      • Installing rebar, pouring, and stripping Generator Pad and footings
      • Forming and installing rebar at one retaining wall
    • ODF&W Parking and Sidewalks:
      • Installing balance of storm work
      • Start installing pole base and electrical
    • Ramp:
      • Installing bentonite and fluid-applied waterproofing
  • SITEWORK & UTILITIES
    • Install potable water and fire water laterals

 

Primary construction activities for the week of 05/27 thru 05/31 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • ROOFING
    • High Roof Auditorium:
      • Continue installing roof
    • Evacuation Ramp:
      • Finish installing handrails
      • Finish installing expansion joint
      • Hot rubber roofing postponed to following week
    • Penthouses:
      • Continue installing framing
    • Lab High Roof West:
      • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
    • Lab Wing – North Elevation:
      • Finish installing air and water barrier
      • Continue installing flashings at pop outs
      • Start installing temp window protection
    • Lab Wing – East Elevation:
      • Finish installing window steel at pop outs
      • Continue installing flashings at pop outs and air & water barrier
    • Lab Wing – South Elevation:
      • Continue installing steel studs
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
      • Finish installing exterior gyp
      • Continue installing window steel at window head & sill, flashings, and air & water barrier
    • Lab Wing – North Elevation:
      • Finish installing steel studs
      • Start installing exterior gyp
    • Lab Wing – East Elevation:
      • Start installing steel studs
    • Lab Wing – South Elevation:
      • Finish installing top / bottom track and studs
    • Auditorium – South Elevation:
      • Finish installing steel stud floor clips
      • Start installing steel studs
    • Auditorium – West Elevation:
      • Start installing steel stud floor clips
  • WINDOWS & SIDING
    • Lab Wing – West Elevation:
      • Finish installing flashings, and trim
    • Lab Wing – North Elevation:
      • Start installing vertical Z girt and windows
  • INTERIOR BUILDOUT
    • Mechanical & Back of House:
      • Finish installing hollow metal doors
      • Continue framing walls
    • Lab Wing Level 2 – Rough-in:
      • Continue installing MEP in Labs
      • Start installing hollow metal doors
    • Mechanical & Back of House:
      • Finish installing hollow metal doors
    • Stair 1:
      • Continue finishing interior
  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101:
      • Layout and excavate for Generator Pad and footings and forming generator pad and footings
    • ODF&W Parking and Sidewalks:
      • Finish installing erosion control and site fencing
      • Excavating Rain Garden #2
      • Excavating public rain garden
      • Installing storm at Manhole #1 and storm chambers
    • Ramp:
      • Forming, installing rebar, pouring, and stripping lower corbel
  • ROOFING
    • High Roof Auditorium
      • Continue installing roof
    • Evacuation Ramp
      • Continue installing handrails
      • Finish installing expansion joint
      • Start installing hot rubber roofing
    • Lab High Roof West
      • Continue installing roof
    • Penthouse
      • Installing framing
  • FRAMING SHEETING (2nd & 3rd Floor)
    • Lab Wing West & SW Elevation:
      • Installing temp window protection (if needed)
    • Lab Wing North Elevation:
      • Finish installing air and water barrier
      • Continue installing window steel at pop outs and flashing at pop outs
    • Lab Wing East Elevation:
      • Installing exterior gyp and window steel at pop outs
      • Start installing flashing at pop outs and air & water barrier
    • Lab Wing South Elevation:
      • Start installing steel studs
    • Penthouses:
      • Finish installing framing
  • FRAMING SHEETING (1st Floor)
    • Lab Wing West Elevation
      • Installing exterior gyp
      • Start installing window steel at window head & sill, flashing, and air & water barrier
    • Lab Wing North Elevation
      • Installing steel studs
      • Start installing exterior gyp
    • Lab Wing East Elevation
      • Finish installing top / bottom track and studs
      • Start installing steel studs
    • Lab Wing South Elevation:
      • installing top / bottom track and studs
    • Auditorium Misc. Steel and Wind Girts:
      • Setting Innovation Lab window steel, S&W wind girts, and overhead door steel
    • Auditorium South Elevation:
      • Finish installing steel stud floor clips
      • Start installing steel studs
  • WINDOWS & SIDING
    • West Elevation
      • Finish installing backer rods & caulking, flashing, and trim
      • Start installing glass, pressure bar, and siding horizontal cleat
  • INTERIOR BUILD OUT
    • Mechanical & Back of House
      • Placing all housekeeping pads and installing hollow metal doors
      • Start framing walls
    • Rough In 2nd Floor
      • Laying out walls and wall penetrations
      • Start installing MEP in Labs
  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101
      • Finish installing electrical and chilled water
      • Backfilling for electrical and chilled water
    • ODF&W Parking and Sidewalks
      • Installing erosion control and site fencing at EOW
Primary construction activities for the week of 05/13 thru 05/17 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Roofing
    • Evacuation Ramp
      • Continue Installing handrails
      • Installing expansion joint
    • Lab High Roof West
      • Continue installing roof
  • Framing Sheeting (2nd & 3rd Floor)
    • Lab Wing West & SW Elevation:
      • Finish installing flashing at pop-outs
      • Installing temp window protection as needed
    • Lab Wing North Elevation:
      • Finish installing exterior gyp
      • Continue installing air and water barrier, window steel at pop outs, and flashing at pop outs
    • Lab Wing East Elevation
      • Installing steel studs
    • Penthouses
      • Finish installing framing
  • Framing Sheeting (1st Floor)
    • Auditorium Misc. Steel and Wind Girts
      • Finish setting Auditorium mezzanine steel
    • Auditorium East Elevation
      • Finish installing steel stud floor clips
    • Auditorium South Elevation
      • Installing steel stud floor clips
    • Auditorium West Elevation
      • Installing steel stud floor clips
    • Lab Wing West Elevation
      • Installing top / bottom track and studs
    • Lab Wing North Elevation
      • Installing top / bottom track
  • Windows and Siding
    • West Elevation
      • Finish installing vertical Z Girt and windows
      • Finish installing backer rods and caulking
      • Start installing flashing and trim
  • Site Improvements
    • Mechanical Enclosure M0101
      • Start installing electrical and chilled water
    • Ramp
      • Installing Bentonite and fluid applied waterproofing, foundation drain, back fill and grade for foam
      • Finish installing foam