Primary construction activities for the week of 05/25 thru 05/29 will consist of the following:
| * = Activity delayed |
- ROOFING
 - Install Tsunami Signs:
- No Activities this Upcoming Week.
 
 
- INTERIOR BUILDOUT
 - Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
- Finish Third Coat Delay
 
- Andersen Punch
 
- Correct Punch
 
- O/A Punch
 
 
- Common Spaces All Levels – Stair Three Finish Work:
- No Activities this Upcoming Week.
 
 
- Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
- Complete Punch
 
- O/A Punch
 
- Complete O/A Punch
 
 
- Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Complete Punch
 
- O/A Punch
 
- Complete O/A Punch
 
 
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Complete Punch
 
- O/A Punch
 
- Complete O/A Punch
 
 
- Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
- Complete Punch
 
- O/A Punch
 
- Complete O/A Punch
 
 
- Commons Wing – Auditorium:
- Cure out Wood Floor and Seating
 
 
- Commons Wing – Innovation Lab:
- Finish Installing Lights and MEP Finishes*
 
- Andersen Punch
 
 - Commons Wing – Level 2 – Design 3D & Art Studio:
- Correct O/A Punch
 
 
- Commons Wing – Level 2 – Sound Control & Vestibules:
- Install New Cooling to SC Room
 
 
- Commons Wing – Level 2 – Perforated Drywall & Sound Control:
- Install Expansion Joints in Floor
 
 
- Lab Wing – Level 1 – Classrooms:
- Third Coat Delay
 
- Andersen Punch
 
- Correct Andersen Punch
 
 
- Lab Wing – Level 2 – Common Spaces:
- Andersen Punch*
 
 
- Lab Wing – Level 2 – Lab Area:
- No Activities this Upcoming Week.
 
 
- Lab Wing – Level 2 – Offices and Conference Rooms:
- Correct O/A Punch
 
 
- Common Spaces – Level 3
- Install Ceiling Sound Baffles
 
- Andersen Punch
 
 
- Lab Wing – Level 3
- Paint Third Coat Delay
 
- Install Balance of Tiles
 
 
- Offices and Conference Rooms – Level 3
- Andersen Punch
 
 
- East Penthouse Storage – Roof Level
- O/A Punch
 
 
- INTERIOR BUILDOUT
 - Elevator 1:
- Finish Workman’s Service Use
 
 - Elevator 2:
- Finish Installing Elevator*
 
 
- SITE IMPROVEMENTS
 - Phase 3 West Site Improvements:
 
No Activities this Upcoming Week