Primary construction activities for the week include:
Deep Soil Mixing continues at the Lab Wing.
Grinding of DSM columns to required elevation.
Below is an up to date schedule.
Finance and Administration / Design and Construction
Primary construction activities for the week include:
Deep Soil Mixing continues at the Lab Wing.
Grinding of DSM columns to required elevation.
Below is an up to date schedule.
Primary construction activities for the week of 8/20 thru 8/24 will consist of:
Below is an up to date construction schedule:
Construction Activities for the following week include:
Continued Deep Soil Mixing of for the Lab Wing.
Grinding of DSM columns to correct elevation.
Attached below is an up-to-date schedule,
Primary construction activities for this week will include:
Continued Deep Soil Mixing for the Lab Wing. Expect constant vibrations.
Grinding of Deep Soil Mixing columns to final elevation.
Construction Activites include continued DSM drilling with which consistent vibration and noise can be expected.
Primary construction activities for this week will include:
Continued Deep Soil Mixing for the Commons Wing. Expect constant vibrations.
Trenching for fiber optic lines will be completed this week.
Water will be switched to new water line.
Below is an updated schedule for the project.
Primary construction activities for this week will include:
Deep Soil Mixing test panels to begin Tuesday transitioning into production panels by the end of the week
Vac-excavation and trenching near Guinn Librar for fiber optic lines to vault to take place starting Monday. This will impact East access road between project and Guinn Library.
Primary construction activities this week include continued installation of underground utilities and final mobilization of DSM equipment.
Deep Soil Mixing test columns will begin Thursday July 5th, with this expect to hear noise and some possible vibrations.
Primary construction activities for this will include continued mobilization of Deep Soil Mixing equipment throughout the week and a waterline shutdown mid-week.
The waterline shutdown will take place Wednesday June 27th from 5:00 pm to 11:00 pm. This will effect water to the Visitors Center, East Wing, West Wing, Education Wing, Guin Library, NAL RSF, and Housing.
Below is an up to date schedule for the site.
Primary activities this week include continued installation of the new water line. Starting Wednesday June 20th expect to see the arrival of the deep soil mixing equipment. Expect to see several large trucks delivering parts and machinery and parts to set up the drill rig, crane, and mixing plant.
Below is an up to date schedule for the site