Primary construction activities for the week of 10/21 thru 10/25 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
 - High Roof Auditorium:
 
- Lab High Roof West:
- Continue installing roofing
 
 
- Penthouse Framing and Sheathing:
- Installing insulation
 
- Start installing scrim and hat channels
 
 
- WINDOWS & SIDING
 - Auditorium – South Elevation:
- Installing backer rod and caulk
 
- Start installing glass and pressure bar
 
 
- Auditorium – West Elevation:
- Installing backer rod and caulk
 
- Start installing glass and pressure bar
 
 
- Auditorium – North Elevation:
- Finish installing vertical siding MWC
 
 
- Auditorium – East Elevation:
- Finish installing beauty cap and flashing *
 
 
- INTERIOR BUILDOUT
 - Commons Wing – Rough-in Framing:
 - Continue framing bathroom shear walls and walls
 - Finish installing MEP at 2nd floor corridors
 - Installing seat sheathing
 - Start installing balance drywall at 2nd floor walls
 
- Commons Wing – Auditorium:
- Start installing scaffolding for finish and painting
 
 
- Lab Wing – Level 1 Rough-in Remaining:
 - Start installing overhead MEP at OTS
 
- Lab Wing –  Level 2 Rough-in:
- Continue installing cable tray at OTS and Commons
 
 
- Lab Wing – Level 2 – Offices and
Conference Rooms
- Finish installing MEP at ceilings
 
- Start installing grid
 
 
- Lab Wing – Level 2 – Labs:
- Finish installing grid and necessary tiles
 
 
- Lab Wing – Level 2 – Bathrooms and
Hard Lid Rooms
- Finish installing MEP at hard lids.
 
- Start installing gyp walls and lids (contingent on MEP inspection)
 
 
- Lab Wing –  Level 3 Rough-in:
- Continue installing MEP in Labs overhead
 
- Continue framing walls at E/3 then clockwise
 
 
- Roof – West Penthouse ELEV Equip Room:
 - Finish installing fire protection
 - Installing cover for MEP
 
- Roof – East Penthouse Storage, ELEV Lobby, & Staging:
 - Finish finishing Gyp *
 - Stuff and spraying top of wall
 - Installing ceiling OTS insulation
 - Start painting the room
 
- SITE IMPROVEMENTS
 - Courtyard: 
- Finish placing rock for East sidewalk
 
 
Start pouring E