Primary construction activities for the week of 01/13 thru 01/17 will consist of the following:
| * = Activity delayed |
- ROOFING
 - Penthouse Framing and Sheathing:
- Start installing electrical in soffit
 
- Finish framing soffit
 
 
- CANOPIESWest Canopy V0102:Installing soffit and wall panels
 
- INTERIOR BUILDOUT
 - Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
- Finish installing tiling
 
 
- Commons Wing – Level 1 – Bathrooms
& A/V Hard Lid Rooms:
- Start gyping walls and lids
 
 
- Lab
Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
- Start gyping walls and lids
 
 
- Lab
Wing –  Level 3 – Bathrooms and Hard Lid Rooms:
- Installing top out and fire tape
 
 
- Commons Wing – Auditorium:
- Continue installing electrical
 
 
- Commons Wing – Innovation Lab:
- Finish installing MEP in ACT ceiling *
 
- Inspecting MEP in ACT ceiling
 
- Start installing ACT tiles
 
- Start installing Gantry Crane
 
 
- Commons Wing – Level 2 – Design 3D
& Art Studio:
- Installing base *
 
- Installing finish electrical *
 
- Andersen Punch
 
 
- Lab Wing – Level 1 – Commons Spaces, Café,
& Fireplace:
- Gyping all remaining walls at Café and VEST V0102 ceilings
 
- Start finishing walls
 
 
- Lab Wing – Level 2 – Rough-in:
- Continue installing cable tray at OTS and Commons
 
 
- Lab Wing – Level 2 – Commons Spaces:
- Installing casework and windowsills *
 
- Start installing carpet *
 
- Start installing base
 
 
- Lab
Wing – Level 2 – Labs:
- Finishing overhead electrical in Lab Area
 
- Finish applying moisture mitigation
 
 
- Lab
Wing –  Level 2 – Offices and Conference Rooms:
- Finishing MEP in grid *
 
 
- Lab Wing –  Level 3 Rough-in – South:
- Finish installing mechanical hangers, seismic, and piping – then test
 
- Start insulating mechanical
 
 
- Lab Wing –  Level 3 Rough-in – East:
- Finish painting
 
- Start installing mechanical hangers, seismic, and piping
 
 
- Lab Wing –  Level 3 Rough-in – West:
- Finish taping and finishing gyp
 
- Start painting
 
 
- Lab Wing –  Level 3 Rough-in – Core Area Labs:
- Finish installing backing and gyp
 
- Start taping and finish gyp
 
 
- Lab Wing –  Level 3 Rough-in – Commons Spaces
- Continue polishing floors
 
 
- Roof – West Penthouse ELEV Equip Room:
 - Finish installing shaft frame, gyp, and finish
 - Start installing disconnects
 
- Roof – East Penthouse Stor, Elev Lobby
& Staging:
- Start framing walls
 
 
- INTERIOR BUILDOUT
 - Elevator 2:
- Continue installing elevator
 
 
- Stair 1:
- Start cleaning and patching walls and landings *
 
 
- Stair 3:
- Installing precast treads
 
 
- Stair 4:
- Installing down rods and landings
 
- Installing treads and risers