Primary activities next week include continuing to level and grade the site in preparation for Deep Soil Mixing mobilization and setup. Sitework contractor will also begin placing and compacting agg base on the west side of the project adjacent to Marine Science Dr, as well as starting to install new waterline.
June 4th – June 8th Construction Activities
This week primary activities consist of clearing and grubbing of the building footprint area. With this, expect to see trucking activity mid-week to haul off spoils/debris.
Dewatering activates are complete for now. The pond in the swales should be subsided by next week.
May 2018 Construction Activities
Reported by Andersen Construction
Thursday, May 10 – Begin demolition of existing buildings
Monday, May 14 – Construct temporary ODFW driveway. Begin installing dewatering points.
Monday, May 21 – Begin sawcutting for parking lot for sewer installation.