Primary construction activities for the week of 01/27 thru 01/31 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Finish installing electrical in soffit *
- Start gyping soffit *
- INTERIOR BUILDOUT
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Installing electrical trim out *
- Installing grab rails and toilet portions *
- Start installing toilet accessories *
- Commons Wing – Level 1 – Bathrooms &
A/V Hard Lid Rooms:
- Start finishing gyp *
- Lab
Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Start finishing gyp *
- Commons Wing – Auditorium:
- Continue installing electrical
- Commons Wing – Innovation Lab:
- Finish installing MEP in ACT ceiling *
- Inspect MEP in ACT ceiling
- Start installing gantry crane
- Start installing ACT tiles
- Commons Wing – Level 2 – Design 3D &
Art Studio:
- Moving MEP down per RFI_0736
- Inspect MEP in ceilings
- Installing ceiling tiles, base, and electrical
- Lab Wing – Level 1 – Commons Spaces, Café,
& Fireplace:
- Installing gyp all remaining walls and Café and VEST V0102 ceilings
- Finishing walls
- Lab Wing – Level 1 – Classrooms:
- Finish painting walls
- Installing ceiling grid
- Lab Wing – Level 2 – Rough-in:
- Finish installing cable tray at OTS and Commons
- Lab Wing – Level 2 – Commons Spaces:
- Start installing base *
- Installing floor boxes
- Lab
Wing – Level 2 – Labs:
- Start installing resilient flooring
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Finishing MEP in grid *
- Lab Wing – Level 3 Rough-in – South:
- Finish installing mechanical hangers, seismic, and piping – then test *
- Continue insulating mechanical
- Lab Wing – Level 3 Rough-in – Northeast:
- Finish installing mechanical hangers, seismic, and piping – then test
- Lab Wing – Level 3 Rough-in – Northwest:
- Continue installing mechanical hangers, seismic, and pipe
- Lab Wing – Level 3 Rough-in – Core Area Labs:
- Finish taping and finish gyp
- Painting
- Start installing mechanical hangers, seismic, and pipe
- Lab Wing – Level 3 Rough-in – Commons Spaces
- Continue polishing floors
- INTERIOR BUILDOUT
- Elevator 1 (mistakenly
had 2 on previous reports):
- Continue installing elevator
- Stair 1:
- Continue cleaning and patching walls and landings
- Stair 3:
- Start installing wood railings
- Stair 4:
- Grinding and finishing welding
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Installing West storm chamber
- Start installing storm water planters
- Stair 1:
- Continue cleaning and patching walls and landings