Primary construction activities for the week of 01/20 thru 01/24 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Finish installing electrical in soffit
- Finish framing soffit and start gyping soffit
- CANOPIESWest Canopy V0102:Finish installing soffit and wall panels
- INTERIOR BUILDOUT
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Installing electrical trim out
- Installing grab rails and toilet portions
- Start installing toilet accessories
- Commons Wing – Level 1 – Bathrooms
& A/V Hard Lid Rooms:
- Finish gyping walls and lids
- Start finishing gyp
- Lab
Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Finish gyping walls and lids
- Start finishing gyp
- Commons Wing – Auditorium:
- Continue installing electrical
- Commons Wing – Innovation Lab:
- Start installing MEP in ACT ceiling *
- Commons Wing – Level 2 – Design 3D
& Art Studio:
- Installing base pushed out until end of month *
- Installing finish electrical pushed out until end of month *
- Andersen Punch pushed out until first week of February *
- Finish finishing drywall and paint below window
- Installing ceiling grid and MEP in ceiling
- Commons Wing – Level 2 – Sound Control
and Vestibules:
- Painting
- Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
- Framing hard lid at Café and VEST V01012
- Finishing MEP in hard lid at Café and VEST V0102
- Lab Wing – Level 1 – Classrooms:
- Start painting walls
- Lab Wing – Level 2 – Rough-in:
- Continue installing cable tray at OTS and Commons
- Lab Wing – Level 2 – Commons Spaces:
- Finishing installing carpet
- Start installing base *
- Lab
Wing – Level 2 – Labs:
- Finishing overhead electrical in Lab Area *
- Finish applying moisture mitigation *
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Finishing MEP in grid *
- Lab Wing – Level 3 Rough-in – South:
- Finish installing mechanical hangers, seismic, and piping – then test *
- Start insulating mechanical *
- Lab Wing – Level 3 Rough-in – Northeast:
- Continue installing mechanical hangers, seismic, and piping
- Lab Wing – Level 3 Rough-in – Northwest:
- Finish painting
- Start installing mechanical hangers, seismic, and pipe
- Lab Wing – Level 3 Rough-in – Core Area Labs:
- Continue taping and finish gyp
- Lab Wing – Level 3 Rough-in – Commons Spaces
- Continue polishing floors
- Roof – West Penthouse ELEV Equip Room:
- Finish installing shaft frame, gyp, and finish *
- Start installing disconnects *
- Roof – East Penthouse Stor, Elev Lobby
& Staging:
- Continue framing walls
- Start installing MEP in walls
- INTERIOR BUILDOUT
- Elevator 2:
- Continue installing elevator
- Stair 1:
- Start cleaning and patching walls and landings *
- Stair 3:
- Installing precast treads *
- Stair 4:
- Finish installing treads and risers
- Start installing handrails