Primary construction activities for the week of 12/16 thru 12/20 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Installing electrical in soffit
  • CANOPIESCommons Wing Soffit:Continue installing trim and metal soffit panels
  • Lab Wing Soffit:Finish installing trim and wood soffit
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Finishing siding
  • INTERIOR BUILD-OUT
  • Commons Wing – Auditorium:
    • Start finishing balance of walls
  • Commons Wing – Innovation Lab:
    • Installing MEP in ACT ceilings
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish gyping walls and lids
    • Start finishing gyp
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Installing ceiling tiles and finishing electrical
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Installing MEP in Sound Control ceiling
    • Inspecting MEP in Sound Control ceiling
    • Start installing ACT tiles
  • Lab Wing – Level 1 – Mechanical & Back of House:
  • Finish installing panels and feeders in electric rooms
  • Lab Wing – Level 1 – Commons Spaces (Café & Fireplace):
    • Installing wall electrical
    • Starting gyp and spray of top out for duct work
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish gyping walls and lids
    • Start finishing gyp
  • Lab Wing –  Level 1 – Classrooms:
    • Start finishing walls
  • Lab Wing – Level 2 – Rough-in:
    • Finish installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Labs:
    • Installing grid and necessary tiles
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • MEP cover inspection
    • Installing ceiling tiles
  • Lab Wing –  Level 3 Rough-in:
    • Finish gyping North walls
    • Finish installing electrical on North and West
    • Continue installing MEP in OTS, offices, and SE area
    • Start finishing walls, OTS insulation, and TOW in North area
    • Start gyping North and West walls
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing disconnects
  • Start installing elevator equipment
  • Roof – East Penthouse Storage, ELEV Lobby, & Staging:
    • Start framing walls