Primary construction activities for the week of 08/19 thru 08/23 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Finish installing furring
    • Install windows
  • Lab Wing Main Roof:
    • Continue installing drain mat foam and rock ballast\
    • Set AHU-401 & EF401 and 402
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • – South Elevation:
    • Finish installing window steel
  • Commons Wing – North Elevation:
    • Finish installing temp window protection (if needed) *
  • Commons Wing – East Elevation:
  • Commons Wing – West Elevation:
    • Finish installing temp window protection if needed
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
  • Lab Wing – North Elevation:
    • Finish installing vertical siding MWC
    • Begin installing beauty cap and flashing
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
    • Begin installing horizontal cleat
    • Finish Installing beauty cap and flashing
  • Auditorium – East Elevation:
    • Finish installing windows
    • Install flashings and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows
    • Begin installing flashing and trim
    • Begin backer rod and caulk
  • Auditorium – North Elevation:
    • Finish Installing windows
    • Begin to install flashing and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • INTERIOR BUILD-OUT
  • Rough in Framing Commons Wing
  • Begin to frame the auditorium fire walls and concrete furring
  • Finish the MEP walls on the 2nd floor
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the first floor
  • Rough in Remaining First Floor:
  • Begin installing MEP in walls
  • Lab Wing Level 2 – Rough-in:
    • Install sound board at OTS Ceilings Donut
    • Paint Top out for MEP to start Donut
    • Finish East and SW
    • Finish the Complete balance of MEP in the walls
    • Begin the Drywall balance of wall labs
  • Roof Level:
  • Finish Painting Room
  • Install the Disconnects
  • Begin Installing Elevator equipment
  • Elevators:
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODFW Parking and Sidewalks:
    • Install signs and stripe
    • Begin Punch Phase one Civil
  • Ramp:
    • Finish back-filling up to Elevation
    • Begin to install Rock at Storm Channel