Primary construction activities for the week of 05/25 thru 05/29 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Install Tsunami Signs:
    • No Activities this Upcoming Week.
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finish Third Coat Delay
    • Andersen Punch
    • Correct Punch
    • O/A Punch
  • Common Spaces All Levels – Stair Three Finish Work:
    • No Activities this Upcoming Week.
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
    • Complete O/A Punch
  • Commons Wing – Auditorium:
    • Cure out Wood Floor and Seating
  • Commons Wing – Innovation Lab:
    • Finish Installing Lights and MEP Finishes*
    • Andersen Punch
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct O/A Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Install New Cooling to SC Room
  • Commons Wing – Level 2 – Perforated Drywall & Sound Control:
    • Install Expansion Joints in Floor
  • Lab Wing – Level 1 – Classrooms:
    • Third Coat Delay
    • Andersen Punch
    • Correct Andersen Punch
  • Lab Wing – Level 2 – Common Spaces:
    • Andersen Punch*
  • Lab Wing – Level 2 – Lab Area:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Correct O/A Punch
  • Common Spaces – Level 3
    • Install Ceiling Sound Baffles
    • Andersen Punch
  • Lab Wing – Level 3
    • Paint Third Coat Delay
    • Install Balance of Tiles
  • Offices and Conference Rooms – Level 3
    • Andersen Punch
  • East Penthouse Storage – Roof Level
    • O/A Punch
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Finish Workman’s Service Use
  • Elevator 2:
    • Finish Installing Elevator*
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:

No Activities this Upcoming Week