Primary construction activities for the week of 05/15 thru 05/22 will consist of the following:
| * = Activity delayed |
- ROOFING
- Install Tsunami Signs:
- No Activities this Upcoming Week.
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
- Install Base*
- Fireplace Install and Grout
- Paint Conduit and Hangers for Wood Ceiling
- Begin Third Coat Delay*
- Install Wood Ceiling
- Common Spaces All Levels – Stair Three Finish Work:
- Finish Installing Panels
- Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Complete O/A Punch
- Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Complete O/A Punch
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Complete O/A Punch
- Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Complete O/A Punch
- Commons Wing – Auditorium:
- Continue Installing Wood Flooring
- Commons Wing – Innovation Lab:
- Finish Installing Lights and MEP Finishes*
- Commons Wing – Level 2 – Design 3D & Art Studio:
- Correct Andersen Punch
- O/A Punch
- Correct O/A Punch
- Commons Wing – Level 2 – Sound Control & Vestibules:
- Install ACT Tiles
- Install Counter Tops
- Install Carpet
- Install Base
- Lab Wing – Level 1 – Classrooms:
- Correct Andersen Punch
- O/A Punch
- Correct O/A Punch
- Lab Wing – Level 2 – Common Spaces:
- Third Coat Delay*
- Andersen Punch*
- Lab Wing – Level 2 – Lab Area:
- Third Coat Delay
- Lab Wing – Level 2 – Offices and Conference Rooms:
- Correct O/A Punch
- Common Spaces – Level 3
- Install Ceiling Tectum Panels and Sound Baffles
- Lab Wing – Level 3
- Install MEP In Cabinets and Countertops
- Install Base
- Finish Electrical
- Offices and Conference Rooms – Level 3
- Paint Third Coat Delay*
- INTERIOR BUILDOUT
- Elevator 1:
- Continue Workman’s Service Use
- Elevator 2:
- Continue Installing Elevator*
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Cure AC
- Cut Out & Pour Manhole Rings