Primary construction activities for the week of 04/27 thru 05/01 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Install Tsunami Signs:
    • Finish Re-waterproofing Area
    • Continue to Reinstall Siding
  • North Elevation:
    • Finish Installing Curtain Wall Center
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Start to Install Wood Ceiling and Lighting
    • Finish Install of Fireplace
    • Install Wood Paneling
    • Install Base
  • Common Spaces All Levels – Stair Three Finish Work:
    • Finish Installing Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Complete Punch
    • O/A Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Plumbing Trim Out
    • Install Electrical Trim Out*
  • Commons Wing – Auditorium:
    • Continue Installing Wood Flooring
  • Commons Wing – Innovation Lab:
    • Install Lights and MEP Finishes*
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch
    • O/A Punch
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Finish Installing MEP in Sound Control Ceiling
    • Inspect MEP in Sound Control Ceiling
    • Install ACT Tiles
    • Install Counter Tops
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • 3rd Coat Delay
    • Andersen Punch
    • Correct Andersen Punch
  • Lab Wing – Level 2 – Common Spaces:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Lab Area:
    • Finish Electrical Install
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Orange South:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • No Activities this Upcoming Week.
  • Common Spaces – Level 3
    • Install Base
    • Continue Installing Floor Boxes and Finish Electrical
  • Lab Wing – Level 3
    • Install Glass in Glass Wall
    • Finish MEP in Ceiling Grid
  • Offices and Conference Rooms – Level 3
    • Finish Electrical
    • Paint 3rd Coat Delay
  • Roof Level – East Penthouse, Lobby and Staging
    • Install MEP in Tops and Trim Room
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing Elevator*
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • No Activities this Upcoming Week.
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Finish Excavating Rain Garden 2
    • Install Balance Curbs and Walks North and South
Print Friendly, PDF & Email

Leave a reply

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong> 

required