Primary construction activities for the week of 04/27 thru 05/01 will consist of the following:
| * = Activity delayed |
- ROOFING
- Install Tsunami Signs:
- Finish Re-waterproofing Area
- Continue to Reinstall Siding
- North Elevation:
- Finish Installing Curtain Wall Center
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
- Start to Install Wood Ceiling and Lighting
- Finish Install of Fireplace
- Install Wood Paneling
- Install Base
- Common Spaces All Levels – Stair Three Finish Work:
- Finish Installing Wood Panels
- Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Complete Punch
- O/A Punch
- Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
- Finish Installing Plumbing Trim Out
- Install Electrical Trim Out*
- Commons Wing – Auditorium:
- Continue Installing Wood Flooring
- Commons Wing – Innovation Lab:
- Install Lights and MEP Finishes*
- Commons Wing – Level 2 – Design 3D & Art Studio:
- Correct Andersen Punch
- O/A Punch
- Commons Wing – Level 2 – Sound Control & Vestibules:
- Finish Installing MEP in Sound Control Ceiling
- Inspect MEP in Sound Control Ceiling
- Install ACT Tiles
- Install Counter Tops
- Commons Wing – Level 2 – Perforated Drywall Sound Control:
- No Activities this Upcoming Week.
- Lab Wing – Level 1 – Classrooms:
- 3rd Coat Delay
- Andersen Punch
- Correct Andersen Punch
- Lab Wing – Level 2 – Common Spaces:
- No Activities this Upcoming Week.
- Lab Wing – Level 2 – Lab Area:
- Finish Electrical Install
- Lab Wing – Level 2 – Offices and Conference Rooms:
- No Activities this Upcoming Week.
- Lab Wing – Level 3 Rough-in – Orange South:
- No Activities this Upcoming Week.
- Lab Wing – Level 3 Rough-in – Blue Northeast:
- No Activities this Upcoming Week.
- Lab Wing – Level 3 Rough-in – Green Northwest:
- No Activities this Upcoming Week.
- Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
- No Activities this Upcoming Week.
- Common Spaces – Level 3
- Install Base
- Continue Installing Floor Boxes and Finish Electrical
- Lab Wing – Level 3
- Install Glass in Glass Wall
- Finish MEP in Ceiling Grid
- Offices and Conference Rooms – Level 3
- Finish Electrical
- Paint 3rd Coat Delay
- Roof Level – East Penthouse, Lobby and Staging
- Install MEP in Tops and Trim Room
- INTERIOR BUILDOUT
- Elevator 1:
- Continue Workman’s Service Use
- Elevator 2:
- Continue Installing Elevator*
- Stair 1:
- No activities this week.
- Stair 2:
- No Activities this Upcoming Week.
- Stair 4:
- No Activities this Upcoming Week.
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Finish Excavating Rain Garden 2
- Install Balance Curbs and Walks North and South