Primary construction activities for the week of 04/06 thru 04/10 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing:
    • Continue Installing Metal Siding
  • Install Tsunami Signs:
    • Install Stainless Steel Sign Holder
    • Re-waterproof Area
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Finish MEP
    • Finish MEP to Fireplace
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels*
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Complete Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Toilet Accessories*
    • Andersen Punch*
    • Complete Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Grab Rails and Toilet Partitions
    • Install Toilet Accessories
    • Andersen Punch
    • Complete Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Plumbing Trim Out
    • Install Electrical Trim Out
    • Start Installing Grab Rails and Toilet Partitions
  • Commons Wing – Auditorium:
    • Finish Seating Framing
    • Install Wood Flooring
  • Commons Wing – Innovation Lab:
    • Correct Andersen Punch*
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch*
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • Install Ceiling Grid in Sound Control
    • Install MEP in Sound Control Ceiling
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • Install Finish MEP
    • 3rd Coat Delay
    • Install ACT Tile
    • Andersen Punch
    • Correct Andersen Punch
  • Lab Wing – Level 2 – Common Spaces:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Lab Area:
    • Install Balance of Tiles and Clouds
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Orange South:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Paint MEPFP in OTS
    • Pipe ID*
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Hydronic Pipe Insulation Delay COVID 19*
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Pipe ID*
  • Common Spaces – Level 3
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3
    • Start Installing Rubber Flooring
  • Offices and Conference Rooms – Level 3
    • Finish Installing Windowsills and Casework*
  • Roof Level – East Penthouse, Lobby and Staging
    • Start Installing Finishes*
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Workman’s Inspection
    • Workman’s Service Use
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • No Activities this Upcoming Week.
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • No Activities this Upcoming Week.
Print Friendly, PDF & Email

Leave a reply

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong> 

required