Primary construction activities for the week of 03/30 thru 04/03 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing:
- Continue Installing Metal Siding
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces,
Café, & Fireplace:
- Install Finish MEP
- Common Spaces All Levels – Stair Three
Finish Work:
- Fab Wood Panels
- Commons Wing – Level 1 – Bathrooms &
A/V Hard Lid Rooms:
- Andersen Punch
- Complete Punch
- Lab
Wing – Level 1 – Bathrooms and Hard Lid
Rooms:
- Finish Installing Toilet Accessories
- Andersen Punch
- Complete Punch
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Install Grab Rails and Toilet Partitions
- Install Toilet Accessories
- Andersen Punch
- Lab
Wing – Level 3 – Bathrooms and Hard Lid
Rooms:
- Finish Painting
- Install Counters
- Install Plumbing Trim Out
- Commons Wing – Auditorium:
- Finish Seating Framing
- Commons Wing – Innovation Lab:
- Correct Andersen Punch
- Commons Wing – Level 2 – Design 3D &
Art Studio:
- Correct Andersen Punch.
- Commons Wing – Level 2 – Sound Control
& Vestibules:
- No Activities this Upcoming Week.
- Commons Wing – Level 2 – Perforated
Drywall Sound Control:
- No Activities this Upcoming Week.
- Lab
Wing – Level 1 – Classrooms:
- Install Base
- Install Finish MEP
- Lab
Wing – Level 2 – Common Spaces:
- No Activities this Upcoming Week.
- Lab
Wing – Level 2 – Lab Area:
- Install Base
- Lab
Wing – Level 2 – Offices and Conference
Rooms:
- No Activities this Upcoming Week.
- Lab Wing – Level 3 Rough-in – Orange South:
- Finish Pipe ID.
- Lab Wing – Level 3 Rough-in – Blue Northeast:
- Finish Pipe ID.
- Lab Wing – Level 3 Rough-in – Green Northwest:
- No activities this upcoming week.
- Lab Wing – Level 3 Rough-in – Purple Core
Area Labs:
- Finish Pipe ID.
- Common Spaces – Level 3
- Install Casework and Windowsills
- Lab Wing – Level 3
- No Activities this Upcoming Week.
- Offices and Conference Rooms – Level 3
- Finish Installing Windowsills and Casework*
- Install Ceiling Tiles
- MEP Cover Inspection
- Roof Level – East Penthouse, Lobby and
Staging
- Paint Room
- Start Installing Finishes
- INTERIOR BUILDOUT
- Elevator 1:
- Continue Workman’s Service Use
- Elevator 2:
- Continue Installing elevator
- Stair 1:
- No activities this week.
- Stair 2:
- No Activities this Upcoming Week.
- Stair 4:
- No Activities this Upcoming Week.
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Seed Areas
- Start Installing Mulch
Very rapidly this site will be famous among all blogging viewers, due to it’s pleasant articles