Primary construction activities for the week of 03/30 thru 04/03 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing:
    • Continue Installing Metal Siding
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Finish MEP
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Andersen Punch
    • Complete Punch
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish Installing Toilet Accessories
    • Andersen Punch
    • Complete Punch
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • Install Grab Rails and Toilet Partitions
    • Install Toilet Accessories
    • Andersen Punch
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish Painting
    • Install Counters
    • Install Plumbing Trim Out
  • Commons Wing – Auditorium:
    • Finish Seating Framing
  • Commons Wing – Innovation Lab:
    • Correct Andersen Punch
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch.
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • No Activities this Upcoming Week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 1 – Classrooms:
    • Install Base
    • Install Finish MEP
  • Lab Wing – Level 2 – Common Spaces:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 2 – Lab Area:
    • Install Base
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • No Activities this Upcoming Week.
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Finish Pipe ID.
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Finish Pipe ID.
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • No activities this upcoming week.
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Pipe ID.
  • Common Spaces – Level 3
    • Install Casework and Windowsills
  • Lab Wing – Level 3
    • No Activities this Upcoming Week.
  • Offices and Conference Rooms – Level 3
    • Finish Installing Windowsills and Casework*
    • Install Ceiling Tiles
    • MEP Cover Inspection
  • Roof Level – East Penthouse, Lobby and Staging
    • Paint Room
    • Start Installing Finishes
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing elevator
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • No Activities this Upcoming Week.
  • Stair 4:
    • No Activities this Upcoming Week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Seed Areas
    • Start Installing Mulch
Print Friendly, PDF & Email

One thought on “CONSTRUCTION ACTIVITIES SCHEDULED FOR UPCOMING WEEK: MARCH 30TH – APRIL 3RD

Leave a reply

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong> 

required