Primary construction activities for the week of 03/23 thru 03/27 will consist of the following:
| * = Activity delayed |
- ROOFING
- Lab High Roof East:
- Continue Installing Roof*
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces,
Café, & Fireplace:
- Continue Installing Tile and Grout at Fireplace
- Common Spaces All Levels – Stair Three
Finish Work:
- Fab Wood Panels
- Commons Wing – Level 1 – Bathrooms &
A/V Hard Lid Rooms:
- Finish Installing Toilet Accessories*
- Andersen Punch
- Complete Punch
- Lab
Wing – Level 1 – Bathrooms and Hard Lid
Rooms:
- Install Grab Rails and Toilet Partitions*
- Start Installing Toilet Accessories
- Andersen Punch
- Complete Punch
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Install Grab Rails and Toilet Partitions
- Install Toilet Accessories
- Lab
Wing – Level 3 – Bathrooms and Hard Lid
Rooms:
- Paint
- Install Tile
- Commons Wing – Auditorium:
- Finish Electrical in Stair Framing
- Commons Wing – Innovation Lab:
- Install Lights and MEP Finishes
- Install Wood Paneling
- Andersen Punch
- Commons Wing – Level 2 – Design 3D &
Art Studio:
- No Activities this Upcoming Week.
- Commons Wing – Level 2 – Sound Control
& Vestibules:
- No Activities this Upcoming Week.
- Commons Wing – Level 2 – Perforated
Drywall Sound Control:
- Install Expansion Joints
- Lab
Wing – Level 1 – Classrooms:
- Install Base
- Install Finish MEP
- Lab
Wing – Level 2 – Common Spaces:
- No Activities this Upcoming Week.
- Lab
Wing – Level 2 – Lab Area:
- Install Balance of Tiles and Clouds
- Lab
Wing – Level 2 – Offices and Conference
Rooms:
- Continue Installing Windowsills and Casework*
- Lab Wing – Level 3 Rough-in – Orange South:
- No Activities this Upcoming Week.
- Lab Wing – Level 3 Rough-in – Blue Northeast:
- No Activities this Upcoming Week.
- Lab Wing – Level 3 Rough-in – Green Northwest:
- No activities this upcoming week.
- Lab Wing – Level 3 Rough-in – Purple Core
Area Labs:
- No Activities this Upcoming Week.
- Common Spaces – Level 3
- Continue Installing Carpet
- Install Base
- Lab Wing – Level 3
- Start Installing Rubber Flooring
- Offices and Conference Rooms – Level 3
- Finish Installing Windowsills and Casework
- Install Ceiling Tiles
- Roof Level – East Penthouse, Lobby and
Staging
- Stuff and Spray Top of Wall
- Install Ceiling OTS Insulation
- Paint Room
- INTERIOR BUILDOUT
- Elevator 1:
- Continue Workman’s Service Use
- Elevator 2:
- Continue Installing elevator
- Stair 1:
- No activities this week.
- Stair 2:
- No Activities this Upcoming Week.
- Stair 4:
- No Activities this Upcoming Week.
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Continue Installing Plants
- Start Seeding Areas