Primary construction activities for the week of 03/16 thru 03/20 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Continue Installing Metal Siding
- Finish Installing Z Girt Insulation and Hat Channels*
- Lab High Roof East:
- Start Installing Roof*
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces,
Café, & Fireplace:
- Continue Installing Tile and Grout at Fireplace
- Common Spaces All Levels – Stair Three
Finish Work:
- Fab Wood Panels
- Commons Wing – Level 1 – Bathrooms
& A/V Hard Lid Rooms:
- Install Electrical Trim Out
- Install Grab Rails and Toilet Partitions*
- Install Toilet Accessories*
- Lab
Wing – Level 1 – Bathrooms and Hard Lid
Rooms:
- Install Grab Rails and Toilet Partitions*
- Start Installing Toilet Accessories
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- No activities this upcoming week.
- Lab
Wing – Level 3 – Bathrooms and Hard Lid
Rooms:
- Finishing Gyp
- Commons Wing – Auditorium:
- Finishing Seat Framing
- Commons Wing – Innovation Lab:
- Install Crane
- Commons Wing – Level 2 – Design 3D
& Art Studio:
- Correct Andersen Punch*
- Commons Wing – Level 2 – Sound Control
& Vestibules:
- No activities this upcoming week.
- Commons Wing – Level 2 – Perforated
Drywall Sound Control:
- Finish Perforated Drywall*
- Lab Wing – Level 1 – Classrooms:
- Start Installing Casework Fume Hoods and Counter tops*
- Lab
Wing – Level 2 – Common Spaces:
- Finish Installing Ceiling and Sound Baffles
- Lab
Wing – Level 2 – Lab Area:
- Install Grid and Necessary Tiles*
- Lab
Wing – Level 2 – Offices and Conference
Rooms:
- Start Installing Windowsills and Casework*
- Lab Wing – Level 3 Rough-in – Orange South:
- Finish Pipe ID*
- Lab Wing – Level 3 Rough-in – Blue Northeast:
- Finish Pipe ID
- Lab Wing – Level 3 Rough-in – Green Northwest:
- No activities this upcoming week.
- Lab Wing – Level 3 Rough-in – Purple Core
Area Labs:
- Finish Pipe ID
- Common Spaces – Level 3
- Install Casework and Windowsills
- Start Installing Carpet
- Lab Wing – Level 3
- Install Grid and Necessary Tiles
- Offices and Conference Rooms – Level 3
- Continue Installing Door Frames
- Finish MEP in Grid
- Install Windowsills and Casework
- Roof Level – East Penthouse, Lobby and
Staging
- Continue Finishing Gyp
- INTERIOR BUILDOUT
- Elevator 1:
- Continue Workman’s Service Use
- Elevator 2:
- Continue Installing elevator
- Stair 1:
- No activities this week.
- Stair 2:
- Paint Walls Lower Landings.
- Stair 4:
- Reinstall Handrail at Siding.
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Install Plants