Primary construction activities for the week of 03/16 thru 03/20 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue Installing Metal Siding
    • Finish Installing Z Girt Insulation and Hat Channels*
  • Lab High Roof East:
    • Start Installing Roof*
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Continue Installing Tile and Grout at Fireplace
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Install Electrical Trim Out
    • Install Grab Rails and Toilet Partitions*
    • Install Toilet Accessories*
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Install Grab Rails and Toilet Partitions*
    • Start Installing Toilet Accessories
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • No activities this upcoming week.
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finishing Gyp
  • Commons Wing – Auditorium:
    • Finishing Seat Framing
  • Commons Wing – Innovation Lab:
    • Install Crane
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch*
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • No activities this upcoming week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Finish Perforated Drywall*
  • Lab Wing – Level 1 – Classrooms:
    • Start Installing Casework Fume Hoods and Counter tops*
  • Lab Wing – Level 2 – Common Spaces:
    • Finish Installing Ceiling and Sound Baffles
  • Lab Wing – Level 2 – Lab Area:
    • Install Grid and Necessary Tiles*
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Start Installing Windowsills and Casework*
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Finish Pipe ID*
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Finish Pipe ID
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • No activities this upcoming week.
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Pipe ID
  • Common Spaces – Level 3
    • Install Casework and Windowsills
    • Start Installing Carpet
  • Lab Wing – Level 3
    • Install Grid and Necessary Tiles
  • Offices and Conference Rooms – Level 3
    • Continue Installing Door Frames
    • Finish MEP in Grid
    • Install Windowsills and Casework
  • Roof Level – East Penthouse, Lobby and Staging
    • Continue Finishing Gyp
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing elevator
  • Stair 1:
    • No activities this week.
  • Stair 2:
    • Paint Walls Lower Landings.
  • Stair 4:
    • Reinstall Handrail at Siding.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Install Plants

Leave a reply

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong> 

required