Primary construction activities for the week of 03/09 thru 03/13 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Continue Installing Metal Siding
- Continue Installing Soffit Standing Seam
- Finish Installing Z Girt Insulation and Hat Channels*
- Lab High Roof East:
- Start Installing Roof*
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces,
Café, & Fireplace:
- Finish Installing Countertops in Café*
- Install Finish MEP*
- Install Tile and Grout at Fireplace*
- Common Spaces All Levels – Stair Three
Finish Work:
- Fab Wood Panels
- Commons Wing – Level 1 – Bathrooms &
A/V Hard Lid Rooms:
- Install Grab Rails and Toilet Partitions*
- Install Toilet Accessories*
- Andersen Punch
- Lab
Wing – Level 1 – Bathrooms and Hard Lid
Rooms:
- Install Grab Rails and Toilet Partitions*
- Start Installing Toilet Accessories
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Start Installing Grab Rails and Toilet Partitions
- Lab
Wing – Level 3 – Bathrooms and Hard Lid
Rooms:
- Continue Finishing Gyp
- Install Tile
- Install Counters
- Start Painting
- Start Installing Plumbing Trim Out
- Commons Wing – Auditorium:
- Continue Finishing Seat Framing
- Commons Wing – Innovation Lab:
- Install ACT Tiles
- Commons Wing – Level 2 – Design 3D &
Art Studio:
- Correct Andersen Punch*
Commons Wing – Level 2 – Sound Control & Vestibules:
- No activities this upcoming week.
- Commons Wing – Level 2 – Perforated
Drywall Sound Control:
- Finish Perforated Drywall*
- Lab
Wing – Level 1 – Classrooms:
- Finish Installing MEP in Ceiling
- Inspect MEP in Ceiling
- Start Installing Casework Fume Hoods and Countertops
- Lab
Wing – Level 2 – Common Spaces:
- Install Ceiling and Sound Baffles
- Lab
Wing – Level 2 – Lab Area:
- Install Grid and Necessary Tiles
- Install Base
- Lab
Wing – Level 2 – Offices and Conference
Rooms:
- Start Installing Windowsills and Casework*
- Lab Wing – Level 3 Rough-in – Orange South:
- Finish Painting MEPFP in OTS*
- Start Pipe ID*
- Lab Wing – Level 3 Rough-in – Blue Northeast:
- Finish Painting MEPFP in OTS*
- Start Pipe ID*
- Lab Wing – Level 3 Rough-in – Green Northwest:
- Finish Electrical in OTS*
- Paint MEPFP in OTS*
- Lab Wing – Level 3 Rough-in – Purple Core
Area Labs:
- Start Electrical in OTS
- Continue Insulating*
- Common Spaces – Level 3
- Continue Polish Floors*
- Roof Level – East Penthouse, Lobby and
Staging
- Install Gyp
- Start Finishing Gyp
- INTERIOR BUILDOUT
- Elevator 1:
- Continue Workman’s Service Use
- Elevator 2:
- Continue Installing elevator
- Stair 1:
- Paint Rails
- Stair 2:
- No activities this week.
- Stair 4:
- No activities this week.
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Install Topsoil
- Install Plants