Primary construction activities for the week of 03/02 thru 03/06 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Continue Installing Metal Siding
- Continue Installing Soffit Standing Seam
- Finish Installing Z Girt Insulation and Hat Channels
- Lab High Roof East:
- Start Installing Roof
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
- Finish Installing Counter tops in Café
- Install Finish MEP
- Common Spaces All Levels – Stair Three
Finish Work:
- Continue Installing Wood Panels*
- Fab Wood Panels
- Commons Wing – Level 1 – Bathrooms
& A/V Hard Lid Rooms:
- Install Electrical Trim Out*
- Install Grab Rails and Toilet Partitions*
- Start Installing Toilet Accessories
- Lab
Wing – Level 1 – Bathrooms and Hard Lid
Rooms:
- Install Electrical Trim Out
- Start Grab Rails and Toilet Partitions
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- No Activities this upcoming Week.
- Lab
Wing – Level 3 – Bathrooms and Hard Lid
Rooms:
- Finish MEP Hard Lids*
- MEP Inspection for Hard Lids*
- Start Gyp Walls and Lids
- Commons Wing – Auditorium:
- Start Finishing Seat Framing
- Commons Wing – Innovation Lab:
- Finish installing ACT tiles*
- Inspect ACT MEP Ceiling
- Commons Wing – Level 2 – Design 3D
& Art Studio:
- Install Base
- Install Finish Electrical
- Third Coat Delay
- Andersen Punch
- Correct Andersen Punch
Commons Wing – Level 2 – Sound Control & Vestibules:
- No activities this upcoming week.
- Commons Wing – Level 2 – Perforated
Drywall Sound Control:
- Finish Perforated Drywall*
- Lab
Wing – Level 1 – Classrooms:
- Continue Installing MEP in Ceiling
- Lab
Wing – Level 2 – Common Spaces:
- Finish Installing Ceiling Tectum Panels and Sound Baffles
- Lab
Wing – Level 2 – Lab Area:
- Continue Installing MEP in Cabinets and Counters
- Install Grid and Necessary Tiles
- Lab
Wing – Level 2 – Offices and Conference
Rooms:
- Finish Installing Doors and Hardware
- Finish MEP Trim Walls and Lids
- Start Installing Windowsills and Casework
- Lab Wing – Level 3 Rough-in – Orange South:
- Finish Painting MEPFP in OTS
- Start Pipe ID*
- Lab Wing – Level 3 Rough-in – Blue Northeast:
- Finish Painting MEPFP in OTS
- Start Pipe ID
- Lab Wing – Level 3 Rough-in – Green Northwest:
- Finish Electrical in OTS
- Paint MEPFP in OTS
- Lab Wing – Level 3 Rough-in – Purple Core
Area Labs:
- Finish TU Test*
- Continue Insulating*
- Common Spaces – Level 3
- Start Polish Floors*
- Roof Level – East Penthouse, Lobby and
Staging
- MEP in Walls
- INTERIOR BUILDOUT
- Elevator 1:
- Continue Workman’s Service Use
- Elevator 2:
- Continue Installing elevator
- Stair 1:
- Finish Prepping Handrails
- Paint Rails
- Stair 2:
- Finish Prepping Handrails
- Paint Rails
- Stair 4:
- No activities this week.
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Finish Install Concrete Walks Building*
- Start Finishing the Irrigation Piping
- Finish Curbs South End
- Start the Rough Grade Parking Lot Install Balance of Rock
- MECHANICAL START-UP AND COMMISSIONING
- Start-Up:
- Commissioning Water System