Primary construction activities for the week of 03/02 thru 03/06 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue Installing Metal Siding
    • Continue Installing Soffit Standing Seam
    • Finish Installing Z Girt Insulation and Hat Channels
  • Lab High Roof East:
    • Start Installing Roof
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finish Installing Counter tops in Café
    • Install Finish MEP
  • Common Spaces All Levels – Stair Three Finish Work:
    • Continue Installing Wood Panels*
    • Fab Wood Panels
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Install Electrical Trim Out*
    • Install Grab Rails and Toilet Partitions*
    • Start Installing Toilet Accessories
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Install Electrical Trim Out
    • Start Grab Rails and Toilet Partitions
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • No Activities this upcoming Week.
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish MEP Hard Lids*
    • MEP Inspection for Hard Lids*
    • Start Gyp Walls and Lids
  • Commons Wing – Auditorium:
    • Start Finishing Seat Framing
  • Commons Wing – Innovation Lab:
    • Finish installing ACT tiles*
    • Inspect ACT MEP Ceiling
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Install Base
    • Install Finish Electrical
    • Third Coat Delay
    • Andersen Punch
    • Correct Andersen Punch

Commons Wing – Level 2 – Sound Control & Vestibules:

  • No activities this upcoming week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Finish Perforated Drywall*
  • Lab Wing – Level 1 – Classrooms:
    • Continue Installing MEP in Ceiling
  • Lab Wing – Level 2 – Common Spaces:
    • Finish Installing Ceiling Tectum Panels and Sound Baffles
  • Lab Wing – Level 2 – Lab Area:
    • Continue Installing MEP in Cabinets and Counters
    • Install Grid and Necessary Tiles
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Finish Installing Doors and Hardware
    • Finish MEP Trim Walls and Lids
    • Start Installing Windowsills and Casework
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Finish Painting MEPFP in OTS
    • Start Pipe ID*
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Finish Painting MEPFP in OTS
    • Start Pipe ID
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Finish Electrical in OTS
    • Paint MEPFP in OTS
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish TU Test*
    • Continue Insulating*
  • Common Spaces – Level 3
    • Start Polish Floors*
  • Roof Level – East Penthouse, Lobby and Staging
    • MEP in Walls
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Continue Workman’s Service Use
  • Elevator 2:
    • Continue Installing elevator
  • Stair 1:
    • Finish Prepping Handrails
    • Paint Rails
  • Stair 2:
    • Finish Prepping Handrails
    • Paint Rails
  • Stair 4:
    • No activities this week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Finish Install Concrete Walks Building*
    • Start Finishing the Irrigation Piping
    • Finish Curbs South End
    • Start the Rough Grade Parking Lot Install Balance of Rock
  • MECHANICAL START-UP AND COMMISSIONING
  • Start-Up:
    • Commissioning Water System

Leave a reply

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong> 

required