Primary construction activities for the week of 02/24 thru 02/28 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Continue Installing Metal Siding
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finish Painting Walls
    • Paint Open to Structure *
    • Install Tile and Grout at Café Back Wall
    • Install Cabinets in Café
    • Start Installing Tile and Grout at Fireplace
  • Common Spaces All Levels – Stair Three Finish Work:
    • Continue Installing Wood Panels*
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Install Plumbing Trim Out
    • Install Electrical Trim Out
    • Install Grab Rails and Toilet Partitions
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Install Plumbing Trim Out
    • Install Electrical Trim Out
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • No Activities this upcoming Week.
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish MEP Hard Lids
    • MEP Inspection for Hard Lids
  • Commons Wing – Auditorium:
    • Continue Installing Acoustical Panels
  • Commons Wing – Innovation Lab:
    • Finish installing ACT tiles
    • Finish Crane Install
    • Start Installing Wood Paneling
    • Start Installing Lights and MEP Finishes
    •  
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Correct Andersen Punch

Commons Wing – Level 2 – Sound Control & Vestibules:

  • No activities this upcoming week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Finish Perforated Drywall*
  • Lab Wing – Level 1 – Classrooms:
    • Finish Installing Casework, Fume hoods, and Counter tops
    • Install Base
  • Lab Wing – Level 2 – Common Spaces:
    • Finish Third Coat Delay
    • Start Andersen Punch
  • Lab Wing – Level 2 – Lab Area:
    • Continue Installing Lab Casework and Fume hoods
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Andersen Punch
    • MEP Cover Inspection
    • Start Installing Ceiling Tiles
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Electrical in OTS
    • Paint MEPFP in OTS
    • Start Pipe ID
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • Finish Insulating
    • Electrical in OTS
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Finish TU Test
    • Finish Insulating
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish TU Test*
    • Finish Insulating
  • Common Spaces – Level 3
    • Start Polish Floors*
  • Roof Level – East Penthouse, Lobby and Staging
    • Install Gyp
    • Start Finishing Gyp
  • INTERIOR BUILDOUT
  • Elevator 1:
    • Workman’s Inspection*
    • Workman’s Service Use
  • Elevator 2:
    • Continue Installing elevator
  • Stair 1:
    • Paint Walls Lower Landings
    • Start to Prep Handrails
  • Stair 2:
    • Start Cleaning and Patching Walls and Landings
  • Stair 4:
    • No activities this week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Finish Installing Electrical Conduits OEG*
    • Finish Install Concrete Walks Building*
    • Start to Dig RG#1 and Clean up South Side Bank