Primary construction activities for the week of 02/17 thru 02/21 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Install Z Girt Insulation and Hat Channels*
    • Install Metal Siding
  • INTERIOR BUILDOUT
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Finishing walls *
    • Paint Walls
    • Paint Open to Structure
  • Common Spaces All Levels – Stair Three Finish Work:
    • Fab Wood Panels
    • Install Wood Panels*
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Install Counters
    • Finish Install Tile
  • Lab Wing – Level 1 – Bathrooms and Hard Lid Rooms:
    • Install Counters
    • Finish Install Tile
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
    • No Activities this upcoming Week.
  • Lab Wing – Level 3 – Bathrooms and Hard Lid Rooms:
    • Finish Framing Hard Lids
    • Start MEP Hard Lids
  • Commons Wing – Auditorium:
    • Finish Install 1.5” Metal Deck*
    • Paint all Walls
    • Start Install Acoustical Panels
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
    • Inspect MEP in ACT ceiling *
    • Start installing ACT tiles *
    • Start Crane Install*
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Install ceiling tiles*
    • Install Base*
    • Install Finish Electrical*
    • Third Coat Delay*
    • Andersen Punch*
  • Commons Wing – Level 2 – Sound Control & Vestibules:
    • No activities this upcoming week.
  • Commons Wing – Level 2 – Perforated Drywall Sound Control:
    • Finish the Install Perforated Drywall
    • Finish Perforated Drywall
  • Lab Wing – Level 1 – Classrooms:
    • Install MEP in Ceiling*
    • Inspect MEP in Ceiling*
  • Lab Wing – Level 2 – Common Spaces:
    • Finish the Install Base
    • Start and Finish Install Floor Boxes
    • Start Install Ceiling Tectum Panels and Sound Baffles
  • Lab Wing – Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
    • Finish Install Base
    • Start Install Doors and Hardware*
  • Lab Wing – Level 3 Rough-in – Orange South:
    • Finish Insulate
    • Electrical in OTS
  • Lab Wing – Level 3 Rough-in – Blue Northeast:
    • TU Test
    • Start Insulate
  • Lab Wing – Level 3 Rough-in – Green Northwest:
    • Finish Duct and TU Install
    • Start TU Test
    •  
  • Lab Wing – Level 3 Rough-in – Purple Core Area Labs:
    • Finish Duct and TU Install*
    • Start TU Test*
  • Common Spaces – Level 3
    • Start Polish Floors
  • Roof Level – East Penthouse, Lobby and Staging
    • Finish MEP in Walls*
  • INTERIOR BUILDOUT
  • Elevator 1:
    • MEP and Cap Screw
    • Workmans Inspection
  • Elevator 2:
    • Installing elevator
  • Stair 1:
    • Finish cleaning and patching walls and landings*
  • Stair 4:
    • No activities this week.
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Install Electrical Conduits OEG*
    • Finish Install Light Pole Foundations*
    • Start Install Concrete Walks Building*
    • Seat Wall
    • Prep Grade ADA Stalls
    • ADA Parking Stalls