Primary construction activities for the week of 02/17 thru 02/21 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Install Z Girt Insulation and Hat Channels*
- Install Metal Siding
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces,
Café, & Fireplace:
- Finishing walls *
- Paint Walls
- Paint Open to Structure
- Common Spaces All Levels – Stair Three
Finish Work:
- Fab Wood Panels
- Install Wood Panels*
- Commons Wing – Level 1 – Bathrooms
& A/V Hard Lid Rooms:
- Install Counters
- Finish Install Tile
- Lab
Wing – Level 1 – Bathrooms and Hard Lid
Rooms:
- Install Counters
- Finish Install Tile
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- No Activities this upcoming Week.
- Lab
Wing – Level 3 – Bathrooms and Hard Lid
Rooms:
- Finish Framing Hard Lids
- Start MEP Hard Lids
- Commons Wing – Auditorium:
- Finish Install 1.5” Metal Deck*
- Paint all Walls
- Start Install Acoustical Panels
- Commons Wing – Innovation Lab:
- Finish installing MEP in ACT ceiling *
- Inspect MEP in ACT ceiling *
- Start installing ACT tiles *
- Start Crane Install*
- Commons Wing – Level 2 – Design 3D
& Art Studio:
- Install ceiling tiles*
- Install Base*
- Install Finish Electrical*
- Third Coat Delay*
- Andersen Punch*
- Commons Wing – Level 2 – Sound Control
& Vestibules:
- No activities this upcoming week.
- Commons Wing – Level 2 – Perforated
Drywall Sound Control:
- Finish the Install Perforated Drywall
- Finish Perforated Drywall
- Lab
Wing – Level 1 – Classrooms:
- Install MEP in Ceiling*
- Inspect MEP in Ceiling*
- Lab
Wing – Level 2 – Common Spaces:
- Finish the Install Base
- Start and Finish Install Floor Boxes
- Start Install Ceiling Tectum Panels and Sound Baffles
- Lab
Wing – Level 2 – Offices and Conference
Rooms:
- Finishing MEP in grid *
- Finish Install Base
- Start Install Doors and Hardware*
- Lab Wing – Level 3 Rough-in – Orange South:
- Finish Insulate
- Electrical in OTS
- Lab Wing – Level 3 Rough-in – Blue Northeast:
- TU Test
- Start Insulate
- Lab Wing – Level 3 Rough-in – Green Northwest:
- Finish Duct and TU Install
- Start TU Test
- Lab Wing – Level 3 Rough-in – Purple Core
Area Labs:
- Finish Duct and TU Install*
- Start TU Test*
- Common Spaces – Level 3
- Start Polish Floors
- Roof Level – East Penthouse, Lobby and
Staging
- Finish MEP in Walls*
- INTERIOR BUILDOUT
- Elevator 1:
- MEP and Cap Screw
- Workmans Inspection
- Elevator 2:
- Installing elevator
- Stair 1:
- Finish cleaning and patching walls and landings*
- Stair 4:
- No activities this week.
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Install Electrical Conduits OEG*
- Finish Install Light Pole Foundations*
- Start Install Concrete Walks Building*
- Seat Wall
- Prep Grade ADA Stalls
- ADA Parking Stalls