Primary construction activities for the week of 02/10 thru 02/14 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Paint Soffit
- Install Z Girt Insulation and Hat Channels
- Install Metal Siding
- INTERIOR BUILDOUT
- Lab Wing – Level 1 – Commons Spaces,
Café, & Fireplace:
- Finishing walls *
- Common Spaces All Levels – Stair Three Finish
Work:
- Measure for Wood Panels
- Fab Wood Panels
- Install Wood Panels
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Start & Finish installing toilet accessories *
- Start Andersen Punch
- Start Complete Punch
- Commons Wing – Level 1 – Bathrooms &
A/V Hard Lid Rooms:
- Paint
- Start Install Tile
- Lab
Wing – Level 1 – Bathrooms and Hard Lid
Rooms:
- Paint
- Start Install Tile
- Lab
Wing – Level 3 – Bathrooms and Hard Lid
Rooms:
- Start Framing Hard Lids
- Commons Wing – Auditorium:
- Start & Finish Install 1.5” Metal Deck*
- Finish Balance of Walls
- Commons Wing – Innovation Lab:
- Finish installing MEP in ACT ceiling *
- Inspect MEP in ACT ceiling *
- Start installing ACT tiles *
- Start Crane Install
- Commons Wing – Level 2 – Design 3D &
Art Studio:
- Install ceiling tiles*
- Install Base
- Install Finish Electrical
- Third Coat Delay
- Andersen Punch
- Commons Wing – Level 2 – Sound Control
& Vestibules:
- Install Ceiling Grid in Sound Control
- Install MEP in Sound Control Ceiling
- Inspect MEP in Sound Control Ceiling
- Commons Wing – Level 2 – Perforated
Drywall Sound Control:
- Install Perforated Drywall
- Finish Perforated Drywall
- Lab
Wing – Level 1 – Classrooms:
- Pain Walls
- Install Ceiling Grid
- Install MEP in Ceiling
- Inspect MEP in Ceiling
- Lab
Wing – Level 2 – Common Spaces:
- Finish Installing Carpet
- Install Base
- Install Floor Boxes
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Finishing MEP in grid *
- Finish Installing Carpet
- Install Base
- Install Doors and Hardware
- Lab Wing – Level 3 Rough-in – Orange South:
- Finish Duct and TU Install*
- Start TU Test*
- Lab Wing – Level 3 Rough-in – Blue Northeast:
- Finish Duct and TU Install*
- Start TU Test*
- Lab Wing – Level 3 Rough-in – Green Northwest:
- Start Duct and TU Install
- Lab Wing – Level 3 Rough-in – Purple Core
Area Labs:
- Finish Duct and TU Install
- Start TU Test
- Roof Level – East Penthouse, Lobby and
Staging
- Start and Finish MEP in Walls
- INTERIOR BUILDOUT
- Elevator 1:
- Continue installing elevator
- MEP and Cap Screw
- Elevator 2:
- Start installing elevator
- Stair 1:
- Finish cleaning and patching walls and landings
- Stair 4:
- Reinstall Handrail at Siding
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Install Electrical Conduits OEG*
- Install Storm Water Planters and West Curbs & ADA
- Install Light Pole Foundations
- Install Irrigation Sleeves
- Start Install Concrete Walks Building