Primary construction activities for the week of 02/03 thru 02/07 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Finish installing electrical in soffit *
- INTERIOR BUILDOUT
- Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Start & Finish installing toilet accessories *
- Start Andersen Punch
- Start Complete Punch
- Commons Wing – Level 1 – Bathrooms &
A/V Hard Lid Rooms:
- Start finishing gyp *
- Lab
Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Start finishing gyp *
- Commons Wing – Auditorium:
- Start & Finish Install 1.5” Metal Deck
- Finish Balance of Walls
- Commons Wing – Innovation Lab:
- Finish installing MEP in ACT ceiling *
- Inspect MEP in ACT ceiling *
- Start installing ACT tiles *
- Commons Wing – Level 2 – Design 3D &
Art Studio:
- Finish Install MEP in ceilings
- Inspect MEP in ceilings*
- Install ceiling tiles*
- Lab Wing – Level 1 – Commons Spaces, Café,
& Fireplace:
- Install Wood Ceiling Support and Hangers
- Finish MEP in Hard Lip Café and Vest 102
- Finish installing gyp all remaining walls and Café and VEST V0102 ceilings
- Finishing walls *
- Lab
Wing – Level 2 – Labs:
- Continue and Finish installing resilient flooring
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Finishing MEP in grid *
- Lab Wing – Level 3 Rough-in – South:
- Finish Duct and TU Install
- Start TU Test
- Lab Wing – Level 3 Rough-in – Northeast:
- Finish Duct and TU Install
- Lab Wing – Level 3 Rough-in – Northwest:
- Finish Mechanical Insulate
- Start Duct and TU Install
- Lab Wing – Level 3 Rough-in – Core Area
Labs:
- Start and Finish Mechanical Insulate
- Start Duct and TU Install
- Lab Wing – Level 3 Rough-in – Commons Spaces
- Continue polishing floors
- INTERIOR BUILDOUT
- Elevator 1 (mistakenly
had 2 on previous reports):
- Continue installing elevator
- Stair 1:
- Continue cleaning and patching walls and landings
- SITE IMPROVEMENTS
- Phase 3 West Site Improvements:
- Finish Install Electrical Conduits OEG
- Finish Install Fire Hydrant, Backflow and Spin Pipe for Irrigation
- Start and Finish Rough Grade Site South and West
- Start and Finish Excavate RG#2 & Adjust OFCB#2