Primary construction activities for the week of 02/03 thru 02/07 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Finish installing electrical in soffit *
  • INTERIOR BUILDOUT
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Start & Finish installing toilet accessories *
    • Start Andersen Punch
    • Start Complete Punch
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Start finishing gyp *
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Start finishing gyp *
  • Commons Wing – Auditorium:
    • Start & Finish Install 1.5” Metal Deck
    • Finish Balance of Walls
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
    • Inspect MEP in ACT ceiling *
    • Start installing ACT tiles *
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Finish Install MEP in ceilings
    • Inspect MEP in ceilings*
    • Install ceiling tiles*
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Install Wood Ceiling Support and Hangers
    • Finish MEP in Hard Lip Café and Vest 102
    • Finish installing gyp all remaining walls and Café and VEST V0102 ceilings
    • Finishing walls *
  • Lab Wing – Level 2 – Labs:
    • Continue and Finish installing resilient flooring
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Finish Duct and TU Install
    • Start TU Test
  • Lab Wing – Level 3 Rough-in – Northeast:
    • Finish Duct and TU Install
  • Lab Wing –  Level 3 Rough-in – Northwest:
    • Finish Mechanical Insulate
    • Start Duct and TU Install
  • Lab Wing – Level 3 Rough-in – Core Area Labs:
    • Start and Finish Mechanical Insulate
    • Start Duct and TU Install
  • Lab Wing –  Level 3 Rough-in – Commons Spaces
    • Continue polishing floors
  • INTERIOR BUILDOUT
  • Elevator 1 (mistakenly had 2 on previous reports):
    • Continue installing elevator
  • Stair 1:
    • Continue cleaning and patching walls and landings
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Finish Install Electrical Conduits OEG
    • Finish Install Fire Hydrant, Backflow and Spin Pipe for Irrigation
    • Start and Finish Rough Grade Site South and West
    • Start and Finish Excavate RG#2 & Adjust OFCB#2