Primary construction activities for the week of 01/27 thru 01/31 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Finish installing electrical in soffit *
    • Start gyping soffit *
  • INTERIOR BUILDOUT
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Installing electrical trim out *
    • Installing grab rails and toilet portions *
    • Start installing toilet accessories *
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Start finishing gyp *
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Start finishing gyp *
  • Commons Wing – Auditorium:
    • Continue installing electrical
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
    • Inspect MEP in ACT ceiling
    • Start installing gantry crane
    • Start installing ACT tiles
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Moving MEP down per RFI_0736
    • Inspect MEP in ceilings
    • Installing ceiling tiles, base, and electrical
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Installing gyp all remaining walls and Café and VEST V0102 ceilings
    • Finishing walls
  • Lab Wing – Level 1 – Classrooms:
    • Finish painting walls
    • Installing ceiling grid
  • Lab Wing – Level 2 – Rough-in:
    • Finish installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Commons Spaces:
    • Start installing base *
    • Installing floor boxes
  • Lab Wing – Level 2 – Labs:
    • Start installing resilient flooring
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Finish installing mechanical hangers, seismic, and piping – then test *
    • Continue insulating mechanical
  • Lab Wing –  Level 3 Rough-in – Northeast:
    • Finish installing mechanical hangers, seismic, and piping – then test
  • Lab Wing –  Level 3 Rough-in – Northwest:
    • Continue installing mechanical hangers, seismic, and pipe
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Finish taping and finish gyp
    • Painting
    • Start installing mechanical hangers, seismic, and pipe
  • Lab Wing –  Level 3 Rough-in – Commons Spaces
    • Continue polishing floors
  • INTERIOR BUILDOUT
  • Elevator 1 (mistakenly had 2 on previous reports):
    • Continue installing elevator
  • Stair 1:
    • Continue cleaning and patching walls and landings
  • Stair 3:
    • Start installing wood railings
  • Stair 4:
    • Grinding and finishing welding
  • SITE IMPROVEMENTS
  • Phase 3 West Site Improvements:
    • Installing West storm chamber
    • Start installing storm water planters
  • Stair 1:
    • Continue cleaning and patching walls and landings