Primary construction activities for the week of 01/20 thru 01/24 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Finish installing electrical in soffit
    • Finish framing soffit and start gyping soffit
  • CANOPIESWest Canopy V0102:Finish installing soffit and wall panels
  • INTERIOR BUILDOUT
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Installing electrical trim out
    • Installing grab rails and toilet portions
    • Start installing toilet accessories
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Finish gyping walls and lids
    • Start finishing gyp
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Finish gyping walls and lids
    • Start finishing gyp
  • Commons Wing – Auditorium:
    • Continue installing electrical
  • Commons Wing – Innovation Lab:
    • Start installing MEP in ACT ceiling *
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Installing base pushed out until end of month *
    • Installing finish electrical pushed out until end of month *
    • Andersen Punch pushed out until first week of February *
    • Finish finishing drywall and paint below window
    • Installing ceiling grid and MEP in ceiling
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Painting
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Framing hard lid at Café and VEST V01012
    • Finishing MEP in hard lid at Café and VEST V0102
  • Lab Wing – Level 1 – Classrooms:
    • Start painting walls
  • Lab Wing – Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Commons Spaces:
    • Finishing installing carpet
    • Start installing base *
  • Lab Wing – Level 2 – Labs:
    • Finishing overhead electrical in Lab Area *
    • Finish applying moisture mitigation *
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Finish installing mechanical hangers, seismic, and piping – then test *
    • Start insulating mechanical *
  • Lab Wing –  Level 3 Rough-in – Northeast:
    • Continue installing mechanical hangers, seismic, and piping
  • Lab Wing –  Level 3 Rough-in – Northwest:
    • Finish painting
    • Start installing mechanical hangers, seismic, and pipe
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Continue taping and finish gyp
  • Lab Wing –  Level 3 Rough-in – Commons Spaces
    • Continue polishing floors
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish *
  • Start installing disconnects *
  • Roof – East Penthouse Stor, Elev Lobby & Staging:
    • Continue framing walls
    • Start installing MEP in walls
  • INTERIOR BUILDOUT
  • Elevator 2:
    • Continue installing elevator
  • Stair 1:
    • Start cleaning and patching walls and landings *
  • Stair 3:
    • Installing precast treads *
  • Stair 4:
    • Finish installing treads and risers
    • Start installing handrails