Primary construction activities for the week of 01/13 thru 01/17 will consist of the following:  

|   * = Activity delayed    |

  • ROOFING
  • Penthouse Framing and Sheathing:
    • Start installing electrical in soffit
    • Finish framing soffit
  • CANOPIESWest Canopy V0102:Installing soffit and wall panels
  • INTERIOR BUILDOUT
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms:
    • Finish installing tiling
  • Commons Wing – Level 1 – Bathrooms & A/V Hard Lid Rooms:
    • Start gyping walls and lids
  • Lab Wing –  Level 1 – Bathrooms and Hard Lid Rooms:
    • Start gyping walls and lids
  • Lab Wing –  Level 3 – Bathrooms and Hard Lid Rooms:
    • Installing top out and fire tape
  • Commons Wing – Auditorium:
    • Continue installing electrical
  • Commons Wing – Innovation Lab:
    • Finish installing MEP in ACT ceiling *
    • Inspecting MEP in ACT ceiling
    • Start installing ACT tiles
    • Start installing Gantry Crane
  • Commons Wing – Level 2 – Design 3D & Art Studio:
    • Installing base *
    • Installing finish electrical *
    • Andersen Punch
  • Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace:
    • Gyping all remaining walls at Café and VEST V0102 ceilings
    • Start finishing walls
  • Lab Wing – Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Commons Spaces:
    • Installing casework and windowsills *
    • Start installing carpet *
    • Start installing base
  • Lab Wing – Level 2 – Labs:
    • Finishing overhead electrical in Lab Area
    • Finish applying moisture mitigation
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Finishing MEP in grid *
  • Lab Wing –  Level 3 Rough-in – South:
    • Finish installing mechanical hangers, seismic, and piping – then test
    • Start insulating mechanical
  • Lab Wing –  Level 3 Rough-in – East:
    • Finish painting
    • Start installing mechanical hangers, seismic, and piping
  • Lab Wing –  Level 3 Rough-in – West:
    • Finish taping and finishing gyp
    • Start painting
  • Lab Wing –  Level 3 Rough-in – Core Area Labs:
    • Finish installing backing and gyp
    • Start taping and finish gyp
  • Lab Wing –  Level 3 Rough-in – Commons Spaces
    • Continue polishing floors
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing shaft frame, gyp, and finish
  • Start installing disconnects
  • Roof – East Penthouse Stor, Elev Lobby & Staging:
    • Start framing walls
  • INTERIOR BUILDOUT
  • Elevator 2:
    • Continue installing elevator
  • Stair 1:
    • Start cleaning and patching walls and landings *
  • Stair 3:
    • Installing precast treads
  • Stair 4:
    • Installing down rods and landings
    • Installing treads and risers