Primary construction activities for the week of 11/25 thru 11/29 will consist of the following:
| * = Activity delayed |
- ROOFING
- Penthouse Framing and Sheathing:
- Continue framing soffit *
- Continue installing metal siding
- CANOPIES West Canopy V102:Finish installing electrical and gyping lids *WRB start delayed
- Commons Wing Soffit:Continue installing trim and metal soffit panels
- Lab Wing Soffit:Start installing trim and metal soffit panels *
- WINDOWS & SIDING
- Auditorium – East Elevation:
- Installing beauty cap and flashing
- Auditorium – North Elevation:
- Continue finishing siding in Armpit
- Auditorium – South Elevation:
- Continue finishing siding
- INTERIOR BUILDOUT
- Commons Wing – Level 1 – Rough-in:
- Finish MEP in walls
- Finish installing balance of drywall
- Continue installing MEP in 1st floor corridors *
- Start installing 1.5” metal deck *
- Commons Wing – Level 2 – Sound Control
and Vestibules:
- Continue finishing lids and walls *
- Lab Wing – Level 1 – Rough-in:
- Continue installing overhead MEP work in OTS
- Lab Wing – Level 1 – Commons Spaces:
- Finish installing MEP in fireplace cavity *
- Starting gyping walls *
- Lab
Wing – Level 1 – Bathrooms and Hard Lid Rooms:
- Finish installing MEP at hard lids *
- MEP inspection for hard lids
- Lab Wing – Level 2 – Rough-in:
- Continue installing cable tray at OTS and Commons
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Continue finishing MEP in grid
- Lab
Wing – Level 2 – Commons Spaces:
- Finish polishing floors
- Lab
Wing – Level 2 – Bathrooms and Hard Lid Rooms:
- Grinding floors
- Lab Wing – Level 3 Rough-in:
- Finish installing gyp top-out at Donut
- Start completing balance of MEP in walls
- Roof – West Penthouse ELEV Equip Room:
- Finish installing shaft frame, gyp, and finish *
- Disconnects install delayed
- Elevator 2:
- Continue installing elevator