Primary construction activities for the week of 10/28 thru 11/01 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Penthouse Framing and Sheathing:
    • Continue Z girts, insulation, and hat channels
    • Start framing soffit
  • CANOPIESEast Canopy V103:Installing frames and glass
  • South Canopy V101:Installing frames and glass
  • West Canopy V102:Finish framingInstalling electrical, and gyping the lidStart installing WRBCommons Wing Soffit:Painting vent in soffitStart installing hat channelLab Wing Soffit:Installing soffit WRB
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Finish installing glass, pressure bar, and vertical siding MWC
  • Auditorium – West Elevation:
    • Finish installing glass, pressure bar, and siding
  • Auditorium – North Elevation:
    • Finish installing glass and pressure bar
    • Siding in Armpit delayed for concrete to finish
    • Start installing beauty cap and flashing
  • Auditorium – East Elevation:
    • Finish siding, beauty cap, and flashing – delayed for concrete work to finish
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Finish MEP in walls on 1st floor
  • Installing scaffolding for MEPFP in Auditorium high ceiling
  • Start installing top for MEP to begin on 1st floor
  • Commons Wing – Level 2 – Designs 3D & Art Studio:
    • Polishing floors
    • Finishing drywall
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Framing hard lids
    • Start installing MEP at hard lids
  • Lab Wing – Level 1 – Rough-in:
  • Finish installing OTS insulation
  • Painting top out and OTS
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Installing grid *
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms
    • Finish installing MEP at hard lids *
    • MEP inspection for hard lids
  • Lab Wing –  Level 3 Rough-in:
    • Continue installing MEP in Labs overhead
    • Continue framing walls at E/3 then clockwise
    • Installing MEP in walls at Doughnut
  • Roof – West Penthouse ELEV Equip Room:
  • Finishing shaft framing, gyp, and finish