Primary construction activities for the week of 10/21 thru 10/25 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab High Roof West:
    • Continue installing roofing
  • Penthouse Framing and Sheathing:
    • Installing insulation
    • Start installing scrim and hat channels
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Installing backer rod and caulk
    • Start installing glass and pressure bar
  • Auditorium – West Elevation:
    • Installing backer rod and caulk
    • Start installing glass and pressure bar
  • Auditorium – North Elevation:
    • Finish installing vertical siding MWC
  • Auditorium – East Elevation:
    • Finish installing beauty cap and flashing *
  • INTERIOR BUILDOUT
  • Commons Wing – Rough-in Framing:
  • Continue framing bathroom shear walls and walls
  • Finish installing MEP at 2nd floor corridors
  • Installing seat sheathing
  • Start installing balance drywall at 2nd floor walls
  • Commons Wing – Auditorium:
    • Start installing scaffolding for finish and painting
  • Lab Wing – Level 1 Rough-in Remaining:
  • Start installing overhead MEP at OTS
  • Lab Wing –  Level 2 Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Offices and Conference Rooms
    • Finish installing MEP at ceilings
    • Start installing grid
  • Lab Wing – Level 2 – Labs:
    • Finish installing grid and necessary tiles
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms
    • Finish installing MEP at hard lids.
    • Start installing gyp walls and lids (contingent on MEP inspection)
  • Lab Wing –  Level 3 Rough-in:
    • Continue installing MEP in Labs overhead
    • Continue framing walls at E/3 then clockwise
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing fire protection
  • Installing cover for MEP
  • Roof – East Penthouse Storage, ELEV Lobby, & Staging:
  • Finish finishing Gyp *
  • Stuff and spraying top of wall
  • Installing ceiling OTS insulation
  • Start painting the room
  • SITE IMPROVEMENTS
  • Courtyard:
    • Finish placing rock for East sidewalk

Start pouring E