Primary construction activities for the week of 07/29 thru 08/02 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Continue to form and pour evacuation ramp and eyebrows
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt
  • Penthouses:
  • Lab High Roof West:
    • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
    • Finish installing flashings and window steel
  • Auditorium – North Elevation:
    • Finish installing exterior gyp
    • Start installation of window steel as well as the air and water barrier
    • Install the flashings
  • Auditorium – East Elevation:Auditorium – South Elevation:
    • to install window steel and flashings**
  • Auditorium – West Elevation:
    • Finish Installing weather barrier, window steel, and flashings
    • Begin installing temp window protection if needed
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding
  • Lab Wing – North Elevation:
    • Continue installing vertical siding
    • Begin installing beauty cap and flashing
  • Lab Wing – East Elevation:
    • Install beauty cap and flashing
  • Lab Wing – South Elevation:
    • Finish installing beauty cap and flashing
    • Begin installing horizontal cleat
  • Auditorium – East Elevation:
    • Install flashings and trim
    • Install backer rod and caulk
    • Begin installing insulation and horizontal cleat
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows, flashings and trim
  • Auditorium – North Elevation:
    • Begin installing vertical Z girt
  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
  • Lab Wing Level 2 – Rough-in:
    • Finish Stuff and spray for STC’s
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • Remove asphalt and fine grade East side
  • Ramp:
    • Finish backfilling up to the fluid applied weather protection
    • Begin the complete bentonite and fluid applied weather protection