Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Continue to form and pour evacuation ramp and eyebrows
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Installing water barrier
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
  • Continue to install temp window protection where needed
  • Auditorium – North Elevation:
    • Finish installing steel studs
    • Start installing exterior gyp
  • Auditorium – East Elevation:
    • Start installing flashings, window steel, and temp window protection (if needed)
      • Auditorium – South Elevation:
    • Continue to install window steel and flashings**
  • Auditorium – West Elevation:
    • Installing weather barrier, window steel, and flashings

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding
  • Lab Wing – North Elevation:
    • Continue installing vertical siding and windows

 

 

 

 

  • Lab Wing – East Elevation:
    • Continue installing vertical siding
    • Installing windows
    • Start installing backer rod and caulk and vertical wood cladding *
  • Lab Wing – South Elevation:
    • Continue installing windows, flashings & trim, and horizontal cleat
  • Auditorium – East Elevation:
    • Start installing windows and vertical Z girt
  • Auditorium – South Elevation:
    • Continue installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish painting top out for MEP to start, start installing panels/feeders in electric rooms and place all house keeping pads.
  • Lab Wing Level 2 – Rough-in:
    • Install MEP in walls
    • Finish installing gyp top out one side of walls at duct locations
    • Continue tape and finish one side top out

 

  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • FRPS west and south curbs
    • Excavating for Rain Garden #2 *

 

Print Friendly, PDF & Email

Leave a reply

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong> 

required