Primary construction activities for the week of 06/03 thru 06/07 will consist of the following:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • ROOFING
    • High Roof Auditorium:
      • Continue installing roof
    • Evacuation Ramp:
      • Finish installing handrails
      • Start Hot rubber roofing
    • Penthouses:
      • Finish installing framing
      • Installing sheathing
    • Lab High Roof West:
      • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
    • Lab Wing – North Elevation:
      • Finish installing flashings at pop outs
      • Continue installing temp window protection (if needed)
    • Lab Wing – East Elevation:
      • Finish installing flashings at pop outs and air & water barrier
    • Lab Wing – South Elevation:
      • Finish installing steel studs
      • Installing exterior gyp
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
      • Finish installing window steel at window head & sill, flashings, and air & water barrier
      • Start installing temp windows (if needed)
    • Lab Wing – North Elevation:
      • Finish installing exterior gyp
      • Start installing window steel at window head & sill, flashings, and air & water barrier
      • Installing temp window protection (if needed)
    • Lab Wing -East Elevation:
      • Finish installing steel studs (was postponed)
      • Installing exterior gyp
      • Start installing window steel at window head & sill, flashings, and air & water barrier at EOW
      • Installing temp window protection (if needed)
    • Lab Wing – South Elevation:
      • Start installing steel studs
    • Auditorium – South Elevation:
      • Continue installing steel studs
      • Start installing exterior gyp
    • Auditorium – West Elevation:
      • Start installing steel studs
    • Auditorium – North Elevation:
      • Start installing steel studs
  • WINDOWS & SIDING
    • Lab Wing – West Elevation:
      • Continue installing siding horizontal cleat
      • Start installing vertical siding wood cladding
    • Lab Wing – North Elevation:
      • Continue installing vertical Z girts and windows
    • Lab Wing – East Elevation:
      • Start installing vertical Z girts and windows
  • INTERIOR BUILDOUT
    • Mechanical & Back of House:
      • Finish framing walls
      • Installing in-wall MEP at Electrical Rooms
      • Start installing gyp top out
    • Lab Wing Level 2 – Rough-in:
      • Continue installing MEP in Labs
      • Start framing walls (starting at E/3 clockwise)
    • Stair 1:
      • Pouring stairs
  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101:
      • Installing rebar, pouring, and stripping Generator Pad and footings
      • Forming and installing rebar at one retaining wall
    • ODF&W Parking and Sidewalks:
      • Installing balance of storm work
      • Start installing pole base and electrical
    • Ramp:
      • Installing bentonite and fluid-applied waterproofing
  • SITEWORK & UTILITIES
    • Install potable water and fire water laterals

 

Print Friendly, PDF & Email