• ROOFING
    • High Roof Auditorium
      • Continue installing roof
    • Evacuation Ramp
      • Continue installing handrails
      • Finish installing expansion joint
      • Start installing hot rubber roofing
    • Lab High Roof West
      • Continue installing roof
    • Penthouse
      • Installing framing
  • FRAMING SHEETING (2nd & 3rd Floor)
    • Lab Wing West & SW Elevation:
      • Installing temp window protection (if needed)
    • Lab Wing North Elevation:
      • Finish installing air and water barrier
      • Continue installing window steel at pop outs and flashing at pop outs
    • Lab Wing East Elevation:
      • Installing exterior gyp and window steel at pop outs
      • Start installing flashing at pop outs and air & water barrier
    • Lab Wing South Elevation:
      • Start installing steel studs
    • Penthouses:
      • Finish installing framing
  • FRAMING SHEETING (1st Floor)
    • Lab Wing West Elevation
      • Installing exterior gyp
      • Start installing window steel at window head & sill, flashing, and air & water barrier
    • Lab Wing North Elevation
      • Installing steel studs
      • Start installing exterior gyp
    • Lab Wing East Elevation
      • Finish installing top / bottom track and studs
      • Start installing steel studs
    • Lab Wing South Elevation:
      • installing top / bottom track and studs
    • Auditorium Misc. Steel and Wind Girts:
      • Setting Innovation Lab window steel, S&W wind girts, and overhead door steel
    • Auditorium South Elevation:
      • Finish installing steel stud floor clips
      • Start installing steel studs
  • WINDOWS & SIDING
    • West Elevation
      • Finish installing backer rods & caulking, flashing, and trim
      • Start installing glass, pressure bar, and siding horizontal cleat
  • INTERIOR BUILD OUT
    • Mechanical & Back of House
      • Placing all housekeeping pads and installing hollow metal doors
      • Start framing walls
    • Rough In 2nd Floor
      • Laying out walls and wall penetrations
      • Start installing MEP in Labs
  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101
      • Finish installing electrical and chilled water
      • Backfilling for electrical and chilled water
    • ODF&W Parking and Sidewalks
      • Installing erosion control and site fencing at EOW