Primary construction activities for the week of 04/01/2019 thru 04/05/2019 will consist of the following:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • East Storage Rm & Northeast Wall (Pour 4):
      • Setting wall, placing rebar, and closing formwork
    • Structural Steel
      • Zone 1:
        • Install metal decking and closure strips
      • Slab on Metal Deck
        • Zone 3 Level 3:
          • Pouring and curing deck for shore removal
        • Zone 5 & ½ Zone 4 Roof:
          • Installing rebar, top embeds, and pouring deck
        • Zone 4 Level 3:
          • Installing blockouts, down embeds, shoring, rebar, and top embeds
        • Zone 3 Level 2:
          • Installing rebar
        • Zone 3 Level 2:
          • Installing blockouts, down embeds, and shoring
        • Zone 4 Level 2:
          • Installing blockouts, down embeds, and shoring
        • Zone 5 Level 2:
          • Installing blockouts and down embeds
        • Slab on Grade
          • Zone 1:
            • Installing blockouts, edge form, importing rock / grade, installing rebar, vapor barrier and top embeds
          • Zone 2:
            • Installing blockouts, edge form, importing rock / grade
            • Digging footings and pouring grout at GL-N
            • Forming, placing rebar, and pouring footing at GL-N
            • Installing vapor barrier, stripping at GL-N, and back filling at GL-N
          • Roofing
            • Lab Wing High Roof:
              • Start forming curbs and crickets at beginning of week.