Primary construction activities for the week of 03/18/2019 – 03/22/2019:

  • Ramp:
    • South Wall West (Pour 3):
      • Finish setting wall and installing rebar. Start closing formwork.
  • Structural Steel:
    • West Lab Wing (Z3):
      • Finish installing headed studs.
    • Center Lab Wing (Z4):
      • Continue installing metal decking and closure strips.
    • East Lab Wing (Z5):
      • Continue bolting, plumbing, and welding.
  • Slab on Metal Deck
    • West Commons Wing Roof (Z2):
      • Installing rebar and shoring.
      • Installing top embeds.
      • Pouring deck at EOW.
    • West Commons Wing L2 (Z2):
      • Pouring deck Mid-Week.
      • Curing deck.
    • West Lab Wing Roof (Z3):
      • Installing blockouts, down embeds, and shoring.
      • Start installing rebar.
    • West Lab Wing L3 (Z3):
      • Installing blockouts, down embeds, and shoring.
    • Mockup:
      • QED performing Water Test.