Primary Construction activities for the week of 2/25/2019 to 3/1/2019:

Ramp:

Storage Room South Wall- Closing formwork, pouring, and stripping.

Northwest Ramp Radius Wall- Closing formwork, pouring, and stripping.

Southwest Ramp Wall- Setting wall formwork.

Structural Steel:

Stair 2- Install clips, hangers, stairs, and handrails.

East Commons (Z1)- Installing metal decking and closure strips.

West Commons (Z2)- Bolting, plumbing, welding, and installing metal decking and closure strips.

West Lab Wing (Z3)- Bolting, plumbing, and welding

Center Lab Wing (Z4)- Bolting, plumbing, and welding

East Lab Wing (Z5)- Erecting, bolting, plumbing, and welding

Mockup:

-Finish Installing windows

-Installing Backing and Flashing on top of Green Girts

-Installing Soffits