Magruder Update 6/18

Currently at the addition of the clinic, the second floor is having the ducting installed for the heating and cooling system and the clinic overall will start to see paint go up on the walls. The latter half of the week, crews will start to install fixtures and the ceiling and the second floor will have the door frames set. In connecting the Clinic to the lobby, the plumbing under the concrete will be completed. As well as the heating demo and electrical rough in, the week will finish up with the concrete slab will be poured back.

The new lecture hall will have the taping of the drywall complete and will start have paint applied at the end of the week, moving into next week. The glass glazing of the building will be installed as well as the glass storefront windows.

Things will be pretty simple this week at the LINAC addition with the plumbing and electrical rough ins will start at the end of the week.

Major prep will be happening for the parking lots will be going on this week. Overall parking lot prep will be occurring, as well as, putting in the new sewer line and prepping the east side of the clinic parking.

 

Leave a Reply

Your email address will not be published. Required fields are marked *