Demo-ing the Lobby: Weekly update 4/8-4/12

This week the existing lobby for the animal hospital as well as the small animal hospital parking lot, which closed the beginning of last week. With the parking lot demo, the tree removal will finish up and existing brush will come out too.

As the clinic gets incorporated with the existing animal hospital, crews will push through the rain to complete the exterior waterproofing and begin the brick veneer.

Things will be short and sweet at the lecture hall this week as crews continue  with roofing, which is the only major project taking place at the lecture hall this week.

Remember to check out the schedule and photos to stay up to date with the Magruder Expansion.